Logentry Text:
--
Summary March 5-6
Day: Smooth data taking on ND3. Nearly 7 hours ABU.
Swing: Beam down for 4 hours due to another RF problem. No major problems on our side - rest is data taking on ND3
Owl: Complete data taking on ND3. 6 hours ABU, but beam somewhat unstable (especially y-position on H01).
8:00 a.m. MCC meeting: It was decided (suddenly) that the attempt to fix the 4-pass Separator for Hall A would be TODAY. So there is NO Maintenance day planned for the rest of the week. We decided to change the plan and use the likely extended downtime to install NH3, do a TE, and polarize. We will HAVE to go to the tagger dump when beam comes back, so if possible we'll do another (set of) Moller run(s). Then take data on negatively polarized NH3.
---
This is a plain text email for clients that cannot display HTML. The full logentry can be found online at https://logbooks.jlab.org/entry/4143896
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/rgc/attachments/20230306/756aee22/attachment-0001.html>
More information about the Rgc
mailing list