[Sbs] [New Logentry] Global hall status

efuchey at jlab.org efuchey at jlab.org
Sat Oct 30 09:10:03 EDT 2021


Logentry Text:
--
A review was conducted to reassess Hall A readiness and determine:

    if the incidents were understood => answer is yes;
    if there were mitigations installed or planned to avoid such incidents to occur again => answer is yes;
    what will be the updated processes and procedures => need, among others, several new OSPs

Review committee issued a list of recommendations and a worklist to complete before resuming operations. Provided the time to perform such work, decision was taken to prepare directly for SBS7 kinematic setting and resume on Monday Nov 8th. 
All shifts till Friday November 5th Owl are cancelled. Shifts from Friday November 5th Day to Sunday November 7 Day are on standby, the time for me to determine when will the target be condensed again.
There are many gaps in the shift schedule from November 8th on so please consider signing for shifts!

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/3934855
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs/attachments/20211030/ca5a8eb0/attachment-0001.html>


More information about the Sbs mailing list