[Sbs_gems] Timeline for SBS GEMs

Bogdan Wojtsekhowski bogdanw at jlab.org
Thu Mar 3 14:22:41 EST 2022


Hi Holly,

I would like to bring your attention that with He-3 target the rates will be low and
needs for improved (final) HV system is not critical. It would be nice to have one-two
divider to be installed for test.
At the same time to make the DAQ installation and commissioning must to be considered.
>From GEn point of view I advocate to move GEM installation as early as possible
because to start experiment in July is very important.
Thanks,

Bogdan
________________________________
From: Sbs_gems <sbs_gems-bounces at jlab.org> on behalf of Holly Szumila-Vance <hszumila at jlab.org>
Sent: Thursday, March 3, 2022 1:59 PM
To: Sbs_gems at jlab.org <Sbs_gems at jlab.org>
Subject: [Sbs_gems] Timeline for SBS GEMs

Hi all,

So it looks like first week of June is still the best time for the crane in Hall A to put the SBS side GEMs in place. We basically have up until then to prepare the layers, and if we are only modifying 1 HV divider then it seems doable to me.

We would want the INFN layers modified by then if possible.

Let me know if you think differently.

-Holly
_______________________________________________
Sbs_gems mailing list
Sbs_gems at jlab.org
https://mailman.jlab.org/mailman/listinfo/sbs_gems
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20220303/5d38c3cd/attachment.html>


More information about the Sbs_gems mailing list