[Sbs_gems] Timeline for SBS GEMs
Bogdan Wojtsekhowski
bogdanw at jlab.org
Thu Mar 3 14:39:11 EST 2022
HI Mark,
My suggestion is about degree of modifications in SBS GEMs which is needed for
run with He-3. In Hall C the target was operational after four months work. With obtained
expertise by the target team it should be about the same in Hall A.
Bogdan
________________________________
From: Mark Jones <jones at jlab.org>
Sent: Thursday, March 3, 2022 2:32 PM
To: Bogdan Wojtsekhowski <bogdanw at jlab.org>; Holly Szumila-Vance <hszumila at jlab.org>; Sbs_gems at jlab.org <Sbs_gems at jlab.org>
Cc: Cates, Gordon D (gdc4k) <gdc4k at virginia.edu>; Averett, Todd D <tdaver at wm.edu>
Subject: Re: Timeline for SBS GEMs
Bogdan,
We need to be realistic. I know that you want to run pion A_LL.
The estimated schedule has been vetted by Gordon and other target experts
and the end of installation by the end of August in realistic. I do not see starting experiment
in July as remotely possible.
We should have a separate meeting to determine what SBS GEMs are a priority to install.
Cheers,
Mark
________________________________
From: Sbs_gems <sbs_gems-bounces at jlab.org> on behalf of Bogdan Wojtsekhowski <bogdanw at jlab.org>
Sent: Thursday, March 3, 2022 2:22 PM
To: Holly Szumila-Vance <hszumila at jlab.org>; Sbs_gems at jlab.org <Sbs_gems at jlab.org>
Cc: Cates, Gordon D (gdc4k) <gdc4k at virginia.edu>; Averett, Todd D <tdaver at wm.edu>
Subject: Re: [Sbs_gems] Timeline for SBS GEMs
Hi Holly,
I would like to bring your attention that with He-3 target the rates will be low and
needs for improved (final) HV system is not critical. It would be nice to have one-two
divider to be installed for test.
At the same time to make the DAQ installation and commissioning must to be considered.
>From GEn point of view I advocate to move GEM installation as early as possible
because to start experiment in July is very important.
Thanks,
Bogdan
________________________________
From: Sbs_gems <sbs_gems-bounces at jlab.org> on behalf of Holly Szumila-Vance <hszumila at jlab.org>
Sent: Thursday, March 3, 2022 1:59 PM
To: Sbs_gems at jlab.org <Sbs_gems at jlab.org>
Subject: [Sbs_gems] Timeline for SBS GEMs
Hi all,
So it looks like first week of June is still the best time for the crane in Hall A to put the SBS side GEMs in place. We basically have up until then to prepare the layers, and if we are only modifying 1 HV divider then it seems doable to me.
We would want the INFN layers modified by then if possible.
Let me know if you think differently.
-Holly
_______________________________________________
Sbs_gems mailing list
Sbs_gems at jlab.org
https://mailman.jlab.org/mailman/listinfo/sbs_gems
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20220303/6ba6a7fe/attachment-0001.html>
More information about the Sbs_gems
mailing list