Today, we (Lars and I) have connected the gas supply line to the BB regulator.
We have placed a ball valve to the lines for the SBS and BB-regulator side to stop gas flow to either of the regulators without affecting flow into the other regulator.
All the new lines/connections were leak-tested using Snoop.

The GEM experts must connect the individual lines from the newly installed filters to the 'BB-GEMs' before starting gas flow in the BB side of the regulator. Currently, the ball valve for the BB side is closed.
I already informed this to Ching.

---

This is a plain text email for clients that cannot display HTML.  The full logentry can be found online at https://logbooks.jlab.org/entry/4315319
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/sbs_gems/attachments/20240823/4c8599cb/attachment.html>


More information about the Sbs_gems mailing list