On 09/08/2011 03:17 PM, Michael Tiefenback wrote:
> These are the requests I made (last May) to swreq for implementation of
> the EPICS readback from the Stanford Research Systems SR620 in the MCC
> equipment room. One message requested that the deed be done, and one
> requested a timetable for implementation so I could plan accordingly.
>
> This is in support of the 12 GeV path length controls baseline plan. I
> thought I had very recently asked for this again (the last few days) but
> I think that the repeated request used a mistaken SR602 (transposed 620
> to 602) model number. The May requests included a hyperlink to the
> online manual so programming info would be available.
>
> Please provide me a timeline for this. I did provide a request in a
> timely fashion for the 6 month down, and I have no record of a response
> to either of these messages from last May.
>
> Thank you for your attention.
>
> Michael Tiefenback

Mike,
    Scott will be providing the software support to get the
device readable through EPICS.  We'll be using the serial
interface, rather than the GPIB.  It's not clear to me yet
whether we'll ask to have the device moved out of the control
room, into the equipment room.

-- 