[Tensor] [EXTERNAL] Run Plan Scripting Assumptions

Elena Long Elena.Long at unh.edu
Tue Mar 14 16:28:45 EDT 2023


Good afternoon,

As promised during today's meeting, I've included the assumptions that I'm currently using for generating the Run Plan. None of these are finalized yet -- the idea is to make the schedule flexible for now for final run time optimization going into the review. As the script matures, I'll also be including time totals information so we can, for instance, see what events are causing the most significant contributions to overhead.

Assumptions for Scheduling:     (All times given in HH:MM:SS)
   Beam Current: 85 nA
   Target Cup Radius: 1.5 cm
   Dose between anneals: 4.00e+15 e/cm^2
   Time Between Anneals: 14:48:09
   Time required for Anneal: 4:00:00
   Time required for target material change: 4:00:00
   Dose between target material changes: 1.00e+17 e/cm^2
   Time between target material changse: 15 days, 10:03:40
   Time required for vector pol. spin-ups: 6:00:00
   Time between each vector pol. spin-up: 2 days, 0:00:00
   Time required for target TE measurements: 4:00:00
   Time required for packing fraction/dilution runs: 1:00:00
   Time required for BCM calibration: 2:00:00
   Beam time between BCM calibrations: 7 days, 12:00:00
   Time required for each Optics run: 4:00:00
   Beam time between Optics runs: 20 days, 0:00:00
   Time required for each Linac change: 8:00:00
   Time required for each Spectrometer Momentum/angle change: 2:00:00
   Time to Tensor Enhance: 0:00:30
   Time to Tensor Unpol: 0:00:10
   Time Between Tensor Pol/Unpol Cycles: 0:10:00


Take care,
Ellie


Elena Long, Ph.D.
Asst. Professor
Dept. of Physics and Astronomy
University of New Hampshire

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/tensor/attachments/20230314/3416648c/attachment-0001.html>


More information about the Tensor mailing list