[Tpe] TPE shielding
Larry Weinstein
weinstei at jlab.org
Fri Jan 28 13:54:22 EST 2011
Dear Dave,
Thank you very much. We will probably want to build this wall during
the next major down time, possibly Tuesday.
- Larry
David Kashy wrote:
> Hello Larry,
> I have verified that we can stack a concrete wall up to 5 ft high and
> 10 ft long on the decking next to the pair spectrometer magnet if
> necessary. I used a block density of 150 lb/cubic ft. I think this is
> what we have.
>
>
> Thanks
> Dave
>
>
>
>>>>>
>>>>>
>>>>> On 1/26/2011 4:55 PM, Larry Weinstein wrote:
>>>>>> Dear Folks,
>>>>>>
>>>>>> Recommendation: In order to be very conservative, build a
>>>>>> concrete wall on the beam left side of the collimator box,
>>>>>> frascati magnet 1, and PS magnet. The wall would be about 10' x
>>>>>> 5' x 1' and require 200 blocks. It should be built during the
>>>>>> next extended down time (Tuesday?) so as not to interfere with
>>>>>> taking data.
>>>>>>
>>>>>> Details: I spoke to Pavel Degtiarenko, the radiation and
>>>>>> shielding expert. He says that there is very little useful data
>>>>>> about the effect of radiation on electronics because the response
>>>>>> of electronics to radiation is highly variable. He also noted
>>>>>> that the existing BPM amplifiers have probably already suffered
>>>>>> some radiation damage and that this damage is cumulative. He
>>>>>> also said that most of the radiation is probably high energy
>>>>>> particles that can be shielded by a shield wall (if we know the
>>>>>> approximate source location.)
>>>>>>
>>>>>> This means that we probably want to add shielding to reduce the
>>>>>> probability of catastrophic BPM failure.
>>>>>>
>>>>>> RadCon gave us the badge readings today (thanks, Becky!).
>>>>>>
>>>>>> 66016 331 1' from top of Acc IOC rack
>>>>>> 66017 197 2.5' from top of Acc IOC rack, in front of concrete wall
>>>>>> 66018 220 2.5' from bottom of Acc IOC rack, in front of
>>>>>> concrete wall
>>>>>> 66019 66 2.5 from top of Acc IOC rack, behind concrete wall
>>>>>> 66020 73 2' from bottom of Acc IOC rack, behind concrete wall
>>>>>> 66023 92 on ioc ptarg
>>>>>>
>>>>>>
>>>>>> 66024 254 in front of new lead wall, 5' from floor
>>>>>> 66025 191 L1-15 on left (upstream) side of IOC
>>>>>> 66026 632 on railing opposite PS
>>>>>>
>>>>>> 66027 230 upstream, beam side of lead wall on ioctorus
>>>>>> 66028 126 downstream, outside of lead wall on ioc torus
>>>>>>
>>>>>> The first column is the badge number, the second is the radiation
>>>>>> dose, and the third is the location.
>>>>>>
>>>>>> A few notes: Badge 66026 with a reading of 632 mr is located
>>>>>> where the radcon photon probe was located before 1/20, on the
>>>>>> railing of the space frame close to the pair spectrometer. The
>>>>>> probe was reading about 50 mr/hr at that location.
>>>>>>
>>>>>> Badge 66019, behind the concrete wall, is located directly on top
>>>>>> of the accelerator BPM amplifiers and right next to the radcon
>>>>>> photon probe which is currently reading 5 mr/hr. This is
>>>>>> consistent with badge 66026.
>>>>>>
>>>>>> badges 66016, 7, and 8 are located on the accelerator BPM
>>>>>> amplifier rack. The highest one (66016) has the highest dose and
>>>>>> has much less of the lead shielding on the lead wall between it
>>>>>> and the beam line. The concrete wall (either 6" or 12") reduces
>>>>>> the rate from about 200 mr to 70 mr (comparing badges 17 and 18
>>>>>> with 19 and 20). (Note that the badges were placed before the
>>>>>> BPE shielding was added.)
>>>>>>
>>>>>> The maximum thickness of the lead wall reduces the dose from 254
>>>>>> (badge 66024) to 92 (badge 66023).
>>>>>>
>>>>>> The radiation level is not much less a little further down-beam
>>>>>> on rack L1-15 (191 mr at badge 25).
>>>>>>
>>>>>> The dose decreases about a factor of two between the upstream
>>>>>> beam side of the lead wall on ioctorus to the downstream outside
>>>>>> of the lead wall.
>>>>>>
>>>>>> Summary: The dose at iocptarg, ioctorus and the accelerator BPM
>>>>>> amplifiers are within a factor of two. The shielding reduces the
>>>>>> dose significantly.
>>>>>>
>>>>>> There is floor space or floor weight capacity to place any more
>>>>>> shielding near the racks. THis means that the only place to add
>>>>>> shielding is near the source. Since the source probably includes
>>>>>> the collimator box, convertor and chicane, we should build a
>>>>>> concrete wall on the beam left side from the PS magnet going as
>>>>>> far upstream as possible.
>>>>>>
>>>>>> --
>>>>>> Sincerely,
>>>>>> Larry
>>>>>>
>>>>>> -----------------------------------------------------------
>>>>>> Lawrence Weinstein
>>>>>> University Professor
>>>>>> Physics Department
>>>>>> Old Dominion University
>>>>>> Norfolk, VA 23529
>>>>>> 757 683 5803
>>>>>> 757 683 3038 (fax)
>>>>>> weinstein at odu.edu <mailto:weinstein at odu.edu>
>>>>>> http://www.lions.odu.edu/~lweinste/ <http://www.lions.odu.edu/%7Elweinste/>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: https://mailman.jlab.org/pipermail/tpe/attachments/20110128/c6325dc2/attachment.html
More information about the Tpe
mailing list