[Ace] New, temporary residents in building 87

Matthew Bickley bickley at jlab.org
Fri May 24 09:58:28 EDT 2019


This is a heads-up for the members of the ACE team, since there might be some support required to help the new residents.


Building 89 is going to be refurbished this year. The plan is for the work to start in June and finish in December. While the renovation is under way the CHL staff will be taking advantage of any available workspaces.  Six of those spaces will be here...four in the "hotel" area adjacent to the west entrance, and two in the area that Chase is currently in. I imagine that the CHL folks will bring their computers, and will only need to plug in to the network. We shall see.


I'll keep you informed as the move date gets closer and the planning firms up.


Matt Bickley