Today's AIPINJ installation forecast .... Sunny with a high chance of wrapping up mech/vac jobs this week!
Please find below our priorities jobs for the week of April 5-9.
We will discuss out-weeks after Steve's 13:30 meeting today.
Update the ATLIS as jobs happen please: http://devweb.acc.jlab.org/CSUEApps/atlis/task/21170
Mon-Tue (April 5-6)
* (CIS) End Wien bake + leak check
Wed-Thu-Fri (April 7-9)
* (Install) Grout Wien pedestals, cut off all thread on Wednesday if possible
* (Install) Finish attaching LCW manifold
* (Install) Fill penetrations – laser room + 58 + 108 as soon as possible
* (Bubba + Shukui) Install and check fit-up of the laser box
* (Phil + Bubba) Install air manifold on girders
* (Electricians + Scott) Install cable tray
* (Electricians + Scott) Bond girders
* (SSG) Install PSS conduit
* (Scott + Shukui) Finish LOSP
* (Joe) – Attach DR dipole "normal" orientation
* (Phil + Joe) – Re-attach Haimson correctors
* (Phil + Joe) – Re-attach QW fixtures
* (Scott) – Attach HV patch box (maybe after cable tray)
* (Danny + Shaun) – Print another giant song sheet print (w/ updated SS prebuncher)
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/aipinj/attachments/20210405/7ce0b9ec/attachment.html>
More information about the Aipinj
mailing list