[Alert_collaboration] [EXTERNAL] Re: ALERT Target Failure and Schedule
Gabriel Charles
gabriel.charles at ijclab.in2p3.fr
Tue Oct 22 11:15:03 EDT 2024
Hi Bob,
Thank you for letting us know.
Have a nice day,
--
Gabriel CHARLES
IJCLab/IN2P3/CNRS, University Paris-Saclay
+33 1 69 15 64 42
Pictures about detectors:
https://urldefense.proofpoint.com/v2/url?u=https-3A__www.instagram.com_particledetectors_&d=DwIFaQ&c=CJqEzB1piLOyyvZjb8YUQw&r=xvIrZb1p8HoRayKD1Sz8zPzqi4-qHfiBCWqgj3oMbOQ&m=-x0IcOM_TknI_R4rXFJqecf9tkyvzkY7ZY2hoy1zuqqs-yAzBsO9VTHzebMt3h1X&s=4AvA9iWZxqUPrwYMYye2K3D2HQT_5FZeRa4O-Cv0KzM&e=
-----Message original-----
De: Bob <alert_collaboration at jlab.org>
à: alert <alert_collaboration at jlab.org>
Cc: Rafayel <rafopar at jlab.org>; Yuri <gotra at jlab.org>; Denny <dinsley at jlab.org>; Morgan <mcookiv at jlab.org>
Envoyé: mardi 22 octobre 2024 13:27 CEST
Sujet : [Alert_collaboration] ALERT Target Failure and Schedule
All,
The target straw failed the overnight test last night and will be replaced today.
Therefore, the schedule shown below will shift until we have a successful target test and survey ALERT per the procedure.
Regards,
Bob
ALERT Schedule
10/17 Leak test target overnight (Morgan)
10/18 Install target and leak check per procedure (Morgan and Bob)
10/21-22 Initial survey
10/23-25 Cable and install boards (Whitney)
10/28 Survey after cabling
10/28 De-cable SVT (Yuri and Rafo)
10/29 Move ALERT to the Hall
10/30 Remove SVT and install ALERT
11/5 Cable and test ALERT (Gabriel)
Bob Miller
Hall B Lead Engineer
(757) 822-9586
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/alert_collaboration/attachments/20241022/1e4c6e7b/attachment-0001.html>
More information about the Alert_collaboration
mailing list