[All_jlau] Lawrence Dr. Construction Update; Rattley Rd. Closure Heads up
deborah magaldi
magaldi at jlab.org
Mon Jun 6 08:39:47 EDT 2016
/This message is being sent on behalf of Jefferson Lab's Facilities
Management and L//ogistics Director,//Rusty Sprouse./
Reconfiguration of the Lawrence Drive entrance to Jefferson Lab is
progressing toward completion of the base asphalt layer. This is
scheduled for completion early in the week of June 13, 2016.The final
pavement layer on the entire length of Lawrence Dr. will occur in late
June or early July. The road will be opened to traffic after the base
layer is completed to accommodate the imminent closure of Rattley Road.
Around June 15, the contractor will start the rebuilding of Rattley
Rd. This effort will take two weeks (weather pending) and involve
closing the road for the entire time.
*Entering the Lab While Rattley Rd. is Closed*
All personnel and personal vehicles, as well as smaller delivery trucks
(smaller than 50'), can use either the Jefferson Ave./Lawrence Dr. or
Jefferson Ave./Hogan Drive entrances while Rattley Rd. is closed. If
using the Hogan Dr. entrance, you will need to either use Lawrence Dr.
(by the ARC building) or Hofstadter Road (by the Support Service Center,
Bldg. 28) to enter the lab.
Cryogenic deliveries are being coordinated to use the Canon Blvd.
entrance. Notify your vendors that if they plan on delivering with a
tractor trailer (50' in length and longer) they are to enter the lab
using Hogan Road. Once on Hogan, they will need to take an immediate
right onto Lawrence Dr. (by the ARC building), then a left onto Pauli
Drive followed by a right at the Pauli/Rattley intersection.
*Exiting the Lab*
All personnel and their personal vehicles, and smaller delivery
vehicles, can exit the lab using Lawrence Dr./Jefferson Ave. or
Hofstadter Rd./Hogan Dr.
Tractor trailers exiting the site will need to use the Lawrence
Dr./Jefferson Ave. exit via Pauli Dr.
Detour signs will be installed.If you have questions about the locations
of any roads mentioned in this email, please visit the lab site plan map
online at: https://www.jlab.org/visitors/visiting/SitePlan.pdf
*Residence Facility Parking During Rattley Rd. Closure*
The parking lot to the SURA Residence Facility will be closed during the
rebuilding of Rattley Rd. Residence Facility patrons and staff can park
in the CEBAF Center parking lot while Rattley Road is closed.
An update notice will be sent out once the specific effective date for
this road work is determined.
All members of the Jefferson Lab community are reminded to stay out of
construction areas.
Questions may be directed to Facilities Management and Logistics
Director, Rusty Sprouse <mailto:sprouse at jlab.org>.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/all_jlau/attachments/20160606/6d35935e/attachment-0001.html>
More information about the All_jlau
mailing list