[Bteam] Schedule for Tues Feb 8
Todd Satogata
satogata at jlab.org
Mon Feb 7 09:15:35 EST 2011
Hi Joe,
> Loosely speaking, we'll take the beam away, put it in the Mott
> polarimeter, set/measure vertical polarization, return beam. This
> all should have little change to injector setup, but would document
> before/after, and if needed make small final adjustments. Altogether
> should be done in <3 hours. *Todd *- what time does
> vert. polarization task start?
Vertical polarization work is scheduled to start at 0800 presently. I
think that time only requires EGG okay to be set in stone. After
discussions with Reza/Arne, the current schedule is
0800 Vert polarization setup (Joe/EGG, 2-3h)
RF recovery (SL)
0L02-3 checkout, other injector warm RF checkout
1030ish Return beam to halls
Hall C Moller measurement
1300ish Reinstall Compton chicane setup
Evaluate Compton backgrounds with current steering/setup
Full-machine RF tuning (Reza) to improve Compton backgrounds
if necessary
This should maximize time to the halls while achieving the Hall C
objectives of vertical polarization setup and Compton chicane back
in. If the Compton backgrounds are still excessive (possible but
unlikely given the halo rates), then we'll have to back out again
and consult with a larger group to develop an intervention plan.
-Todd
--------------+---------------------------+----------------+------------------