Perhaps a more pleasant color scheme and a few bug fixes (still some 
more bugs out there...).   The Mott Upgrade and Peppo tasks are 
populated on this schedule at a low priority.    Since there is nothing 
on the schedule (yet) after collaborative checks, the remaining Peppo 
tasks got placed on shifts after collaborative tests.  Clearly if the 
halls are ready and if this schedule holds true, those shifts labeled as 
Peppo after Collaborative Checks will probably be rescheduled.

I have not created a "CASA" resource and assigned it to some of these 
tasks, clearly that must happen.

Arne

On 09/10/2011 12:13 PM, Arne Freyberger wrote:
> Attached is the latest html version of the startup calendar.   I've 
> migrated away from listing all the subtasks to listing the next level 
> up.  This way you get more broader view of the startup.   The subtasks 
> and resources can be viewed by mousing over the task.
>
> This calendar still reflects the "current" scenario as presented on 
> Aug 31st.
>
> Arne
>
>
> _______________________________________________
> Bteam mailing list
> Bteam at jlab.org
> https://mailman.jlab.org/mailman/listinfo/bteam

-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab           Office: (757) 269-6268
12000 Jefferson Avenue  Cell:   (757) 876-6289
Newport News, VA 23606  Email:  freyberg at jlab.org

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20110910/c737ccf2/attachment-0004.html>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20110910/c737ccf2/attachment-0005.html>


More information about the BTeam mailing list