[Bteam] restoration calendar
Arne Freyberger
freyberg at jlab.org
Mon Sep 19 16:38:27 EDT 2011
Several changes to the restoration calendar have been put in place over
the last few days. Most of the changes are minor, but things did shift
around a bit. The biggest change is the inclusion of the Physics
program at the nominal start date. Collaborative Checks are schedule
for the two days preceding Physics. About five days of float( for
Mott/Peppo) lie between the final ORFP and Collaborative checks.
You can view the restoration calendar at:
http://opsweb.acc.jlab.org/beam_restoration_calendar
This is still the optimistic calendar.....
Arne
--