[Bteam] Thursday is going to be a very full day. Friday won't be much better
Peter Anthony Francis
francis at jlab.org
Wed Apr 18 06:25:32 EDT 2012
I just read Jay B's response, so if there happens to be a access for the
North Linac on Thursday I will be on it, if not, we will just have to wait.
On 4/18/2012 6:23 AM, Peter Anthony Francis wrote:
> Yes, this RF module is in the North Linac. I would need restricted or
> controlled access to replace IPM0R04's RF module on Thursday.
>
>
> On 4/17/2012 8:57 PM, Michael Tiefenback wrote:
>> Please ensure that Pete Francis has opportunity to get the IPM0R04
>> SEE electronics box swapped out during the early access (if
>> possible). It may be in the NL segment. It would be good if he can
>> do that -- the BPM was reading 75% of what it should have read, and
>> it would be great to be able to 1) look at the box's response on the
>> bench, and 2) try the system out with a different electronics box
>> downstairs.
>>
>> Thanks.
>>
>> Michael Tiefenback
>>
>> Jay Benesch wrote:
>>> Feel free to forward this.
>>>
>>> 0700 RadCon survey of SL and then BSY
>>>
>>> 0730 SRF entry into SL for piezo work, estimate 6 hours to complete
>>> http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12322
>>> is the only ATLis I can find
>>>
>>> 0700 injector work in parallel, likely a two hour PEPPO test
>>>
>>> 0745 halls can request of PD controlled or restricted access
>>>
>>> 0900? gun HV off, short injector entry, QE scan, etc. total ~1h
>>>
>>> 0900-1200 ten ARMs will be in refresher course in RadCon trailer
>>>
>>> 1000-1600 additional PEPPO tests
>>>
>>> 1300 begin RF recovery of two zones in NL turned off last week
>>>
>>> 1330 lock up SL and BSY
>>>
>>> 1400 C100 work begins from upstairs
>>>
>>> 1415-1630 BIW tours. Four busloads visiting MCC, FEL, Hall D, ?
>>> Arne, Mike T., Todd S. and Jay talking at MCC.
>>>
>>> 1430 begin RF recovery of six SL zones turned off last week
>>>
>>> 1600 bring up magnets and as much RF as possible
>>> DC power support needed as something will have broken due to
>>> on/off/on cycle
>>> Use BURT and MST to get correct BdLs into magnets
>>>
>>> 1630 spot move, Wien flip and HWien set ~1.5 hours
>>>
>>> 1800 high current setup at 61.6 MeV
>>>
>>> 2000 C100 work ends. Restore 548/linac begins in earnest.
>>> http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12320
>>>
>>> ~2200 first pass beam around with all cavities phased
>>>
>>> ~2359 ready to RF separate first pass to A, third to C. Fifth to B
>>>
>>> Friday
>>>
>>> 0400?? low current beam to A, B, C. C will take under 3uA to ~1300.
>>>
>>> 1300-1700 high current setup to C including C100 tuning as required
>>>
>>> 1300-1600 ten ARMs in refresher course in RadCon trailer
>>>
>>> 1300-1500 Qweak physics meeting
>>> _______________________________________________
>>> Bteam mailing list
>>> Bteam at jlab.org
>>> https://mailman.jlab.org/mailman/listinfo/bteam
More information about the BTeam
mailing list