[Bteam] Thursday is going to be a very full day. Friday won't be much better
Joe Grames
grames at jlab.org
Wed Apr 18 06:49:53 EDT 2012
Hi Pete - Tomorrow's plan didn't include an access to the NL. Of course
the plan can always change if this is important, but a NL access would
slow down the start of beam studies because we'd like the NL in BP
possibly as early at ~7:30am again; barely enough time for the survey.
Joe
Peter Anthony Francis wrote:
> I just read Jay B's response, so if there happens to be a access for the
> North Linac on Thursday I will be on it, if not, we will just have to wait.
>
>
> On 4/18/2012 6:23 AM, Peter Anthony Francis wrote:
>
>> Yes, this RF module is in the North Linac. I would need restricted or
>> controlled access to replace IPM0R04's RF module on Thursday.
>>
>>
>> On 4/17/2012 8:57 PM, Michael Tiefenback wrote:
>>
>>> Please ensure that Pete Francis has opportunity to get the IPM0R04
>>> SEE electronics box swapped out during the early access (if
>>> possible). It may be in the NL segment. It would be good if he can
>>> do that -- the BPM was reading 75% of what it should have read, and
>>> it would be great to be able to 1) look at the box's response on the
>>> bench, and 2) try the system out with a different electronics box
>>> downstairs.
>>>
>>> Thanks.
>>>
>>> Michael Tiefenback
>>>
>>> Jay Benesch wrote:
>>>
>>>> Feel free to forward this.
>>>>
>>>> 0700 RadCon survey of SL and then BSY
>>>>
>>>> 0730 SRF entry into SL for piezo work, estimate 6 hours to complete
>>>> http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12322
>>>> is the only ATLis I can find
>>>>
>>>> 0700 injector work in parallel, likely a two hour PEPPO test
>>>>
>>>> 0745 halls can request of PD controlled or restricted access
>>>>
>>>> 0900? gun HV off, short injector entry, QE scan, etc. total ~1h
>>>>
>>>> 0900-1200 ten ARMs will be in refresher course in RadCon trailer
>>>>
>>>> 1000-1600 additional PEPPO tests
>>>>
>>>> 1300 begin RF recovery of two zones in NL turned off last week
>>>>
>>>> 1330 lock up SL and BSY
>>>>
>>>> 1400 C100 work begins from upstairs
>>>>
>>>> 1415-1630 BIW tours. Four busloads visiting MCC, FEL, Hall D, ?
>>>> Arne, Mike T., Todd S. and Jay talking at MCC.
>>>>
>>>> 1430 begin RF recovery of six SL zones turned off last week
>>>>
>>>> 1600 bring up magnets and as much RF as possible
>>>> DC power support needed as something will have broken due to
>>>> on/off/on cycle
>>>> Use BURT and MST to get correct BdLs into magnets
>>>>
>>>> 1630 spot move, Wien flip and HWien set ~1.5 hours
>>>>
>>>> 1800 high current setup at 61.6 MeV
>>>>
>>>> 2000 C100 work ends. Restore 548/linac begins in earnest.
>>>> http://opsweb.acc.jlab.org/CSUEApps/atlis/task/12320
>>>>
>>>> ~2200 first pass beam around with all cavities phased
>>>>
>>>> ~2359 ready to RF separate first pass to A, third to C. Fifth to B
>>>>
>>>> Friday
>>>>
>>>> 0400?? low current beam to A, B, C. C will take under 3uA to ~1300.
>>>>
>>>> 1300-1700 high current setup to C including C100 tuning as required
>>>>
>>>> 1300-1600 ten ARMs in refresher course in RadCon trailer
>>>>
>>>> 1300-1500 Qweak physics meeting
>>>> _______________________________________________
>>>> Bteam mailing list
>>>> Bteam at jlab.org
>>>> https://mailman.jlab.org/mailman/listinfo/bteam
>>>>
>
> _______________________________________________
> Bteam mailing list
> Bteam at jlab.org
> https://mailman.jlab.org/mailman/listinfo/bteam
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20120418/aefd3cc7/attachment-0002.html>
More information about the BTeam
mailing list