[BTeam] [New Logentry] Saturday Evening CEBAF Status and path towards energy scaling on Monday
freyberg at jlab.org
freyberg at jlab.org
Sat Mar 29 21:15:01 EDT 2014
======== SATURDAY EVENING CEBAF STATUS AND PATH TOWARDS ENERGY SCALING ON ====
======== MONDAY [1] ===========================================================
Lognumber 3278329 [1]. Submitted by freyberg [2] on Sat, 03/29/2014 - 21:14.
+---------+---------+
|Logbooks:|BTLOG [3]|
+---------+---------+
Another CEBAF roller coaster ride. After struggling with pathlength issues,
CEBAF hardware, and optics issues all week, it was a significant accomplishment
to get the optics setup to converge Friday swing. Unfortunately going CW has
illuminated some additional hardware issues with an at present unknown source.
I
hope the accomplishment of getting this optics setup to converged does not get
obfuscated by the hardware issue.
The observation we are presently dealing with is an horizontal jitter on the 2A
SLM and BLM trips at high dispersion points. The nominal conclusion is that
this
is an RF or energy issue. 12 hours of looking at the RF has not found anything
wrong. With some of the diagnostics not quite 100%, there are some blind spots
in our tool set. For example 1A SLM would be useful and BLA waveforms are not
working. So I pass on some important guidance from Mike T. that in the past
some
of these instabilities have been sourced by magnetic issues and other sources.
Indeed discussion of BBU has been heard in the control room as well as some
cursory magnet checks. Nothing is ruled out and I encourage everyone to keep an
open mind as they engage the problem.
With that said, the hall does have a useful low current program which we
switched over to on early Swing shift. The hall program is limited to 2$\mu$A
as
beam currents above result in some vacuum excursions. Parasitic and
opportunistic debugging is encouraged.
The program for Sunday remains the Moller program and the program for Monday is
to perform the energy scaling. On Monday we will be down most of the day-shift
for RF recovery, which is needed as we by-passed a large number of cavities
today in trying to identify the energy jitter source.
The goal for the 1000MeV/linac setup is to send tune-mode beam to Hall-A at
greater than 6GeV. Once this is accomplished (Wednesday?), we could try CW
operations again just to give the Hall-A one more try for the target boiling
test. Who knows, the change in energy might flush out or hide the present
issue.
It all depends on how the energy scaling goes, we might be performing optics
tuning all week. However, I must stress, that establishing 6GeV, tune-mode beam
is a good example of where good enough is good enough. We are not looking for a
perfect setup, just get the beam on target, get the energy required, get some
events to tape and declare victory. What we do after that will be topics of
discussion next week.
Thanks for all the hard work in the control over the past week. One more week
to
go.
[1] https://logbooks.jlab.org/entry/3278329
[2] https://logbooks.jlab.org/user/freyberg
[3] https://logbooks.jlab.org/book/btlog
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20140329/f6f2180f/attachment-0002.html>
More information about the BTeam
mailing list