[BTeam] CEBAF Status and plan overview for the remaining week.
Arne Freyberger
freyberg at jlab.org
Mon Mar 31 15:25:04 EDT 2014
Colleagues:
Today the RFpower staff is recovering as much of the RF system as
possible in preparation for scaling the machine to 2.0GeV/pass
(1GeV/linac). In parallel, the injector experts are investigated if
the beam instability is sourced in the injector. The OTR on the
spectrometer dump shows some energy instability and this might be the
source of our CW woes (https://logbooks.jlab.org/entry/3279059). A
download file, scaled from the all-save from this morning has been
downloaded in the magnets. If we're linear this should be a good
place to start the 2GeV/pass setup.
With that said, it is hoped that the 2GeV/pass beam setup will start
during Swing shift and continue through to Swing on Tuesday. It is
hoped that Supplemental LASO support will terminate before Swing
Tuesday, but just in case I've filled out the shift schedule up to
Thursday Day.
The program over the next for days are (in priority order):
1. E>6GeV to Hall-A dump with target in place, events recorded and
tune-mode beam (*MUST*)
2. Try CW again (assuming the source in the Injector has been
identified and repaired) and establish maximum supportable CW
current up to 100uA. The hall has no need for this anymore, as
they are warming up their target. This test is just for us to learn
what other limits are out there. Spend at most 8h on this. (SHOULD)
3. Beam optics measurements to document this setup. I am working with
Todd to create the list of measurements. This will be the focus of
our efforts Wednesday/Thursday. (SHOULD)
4. If time is available work with the Hall-A to support any remaining
commissioning activities. The major item on the list would be the
Moller commissioning which requires that they get a bipolar supply
for the Moller quad. (SHOULD)
If we have achieved item 1 by Friday 6am, beam will be terminated.
Otherwise the beam program can extend until item 1 has been achieved.
Hall-A has been informed that they will not be receiving beam after the
April Down as we will be focused on the 5.5pass spin-up and
optics/scaling measurements.
Cheers,
Arne
Day Name Date Owl DAY DAY Swing Swing
LASO Supplement LASO Supplement
-------------------------------------------------------------------------------------------
Thursday Mar-27 S. Zhang M. Spata Y. Roblin M. Tiefenback
Friday Mar-28 M. Stutzman A. Freyberger C. Tennant T. Satogata
Saturday Mar-29 V. Morozov J. Benesch D. Douglas G. Krafft
Sunday Mar-30 J. Grames A. Freyberger A. Hofler
-------------------------------------------------------------------------------------------
Monday (1000MeV/pass) Mar-31 M. Ahmad Everyone S. Benson M. Tiefenback
Tuesday Apr-01 J. Benesch T. Satogata Y. Wang A. Freyberger
Wednesday Apr-02 B. Terzic Y. Roblin A. Bogacz M. Tiefenback
Thursday Apr-03 S. Zhang G. Krafft F. Lin A. Godot
Friday Apr-04 NA NA
--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab
12000 Jefferson Avenue Cell: (757) 876-6289
Postal Suite 19 Email: freyberg at jlab.org
Newport News, VA 23606
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20140331/7376b721/attachment-0002.html>
More information about the BTeam
mailing list