[BTeam] Fwd: [On_site_list] Addendum to Oct. 2014 - Sept. 2016 Experiment Schedule - R. Ent/A. Freyberger for the Experiment Scheduling Committee
Arne Freyberger
freyberg at jlab.org
Fri Apr 24 09:11:47 EDT 2015
The run extension provides an opportunity to perform beam studies during
the week days within some constraints. The constraints are:
* Monday May 4th, this days shift should be spent turning off Arcs
3-A, measuring and correcting for any cross talk associated with
these arcs.
* After Monday beam will be terminated at 2R and Beam studies should
not request beam beyond 2R
* Friday May 8th, there will be no beam studies as the tunnel will be
open up in preparation for the IPAC15 tour
* The first week Tues/Wed/Thur may be particularly challenging to
fill with beam studies as IPAC15 will be going on in parallel. If
you are not going to IPAC15, here's your chance.
* With coordination it may be possible to send one-pass beam to Hall-A
during day shifts, for beam studies. Hall-A leadership most
approve/decline this activity.
A strawman beam studies schedule should be discussed, prioritized and
vetted at the next B-team meeting, Tuesday.
Arne
-------- Forwarded Message --------
Subject: [On_site_list] Addendum to Oct. 2014 - Sept. 2016 Experiment
Schedule - R. Ent/A. Freyberger for the Experiment Scheduling Committee
Date: Thu, 23 Apr 2015 16:53:22 -0400
From: deborah magaldi <magaldi at jlab.org>
To: on_site_list at jlab.org
CEBAF operations at Jefferson Lab have now been restored to a 1 GeV/pass
beam energy due to limited CHL availability following an outage. We have
agreed upon an extension of accelerator operations, at one pass only and
up to May 18, as outlined in a schedule addendum posted.
This will accommodate:
- accelerator studies during week days
- HPS operations at 1 GeV beam energy in Hall B during evenings and
weekends, if compatible with 12 GeV installation priorities. We do
foresee 10 hour shifts for 12 GeV work during week days Monday-Friday.
Beam will be turned off from May 8 (Friday morning) until May 9
(Saturday afternoon) for the scheduled IPAC tour. Beam operations will
stop on May 18 at 6 a.m.
An addendum to the schedule has been posted at
https://www.jlab.org/div_dept/physics_division/experiments/schedule.html
_______________________________________________
On_site_list mailing list
On_site_list at jlab.org
https://mailman.jlab.org/mailman/listinfo/on_site_list
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20150424/516e02d1/attachment-0002.html>
More information about the BTeam
mailing list