[BTeam] Startup plan as presented yesterday, it is an evolving plan to accommodate a fluid situation

Arne Freyberger freyberg at jlab.org
Wed Feb 11 09:02:03 EST 2015


Spring 2015 Startup strawman


  Spring 2015 Startup strawman


    1 Spring 2015 StartUp OPS


      1.1 2015-02-11 Wed

 1. Owl
      * SSO
 2. Day
      * Punch list shift
      * NL restricted for Klystron work
 3. Swing
      * Sweep machine and lock up
      * Soak RF
      * Soak Mag


      1.2 2015-02-12 Thu

 1. Owl
      * Soak RF, random RF settings
      * Soak Mag, random MAG settings
      * Sweep and post all service buildings
 2. Day
      * Sweep and post all service buildings
      * Soak RF, LEM 950
      * Soak Mag, Download EDT values
          o Feb2015 startup, design BDLs for the entire machine
            <https://logbooks.jlab.org/entry/3319685>
          o Feb2015_zero_correctors.snap
            <https://logbooks.jlab.org/entry/3319688>
          o Feb2015_doglegs.snap <https://logbooks.jlab.org/entry/3319686>
      * 2-3pm Inj tour
 3. Swing
      * Soak RF/Mag at design settings
      * Inj Model Studies


      1.3 2015-02-13 Fri

 1. Owl - Soak and post
      * Soak RF/Mag at design settings
 2. Day
      * Soak RF/Mag at design settings
      * Warm RF setup
      * keV bunchlength measurement (Poelker/Ahmad)
          o Laser A
          o Laser B
          o Laser C
      * set Wien angle to: 63.972 degrees
      * A1/A2 Transmission Optimization
      * Beam to FC2/Mott
      * bunch length optimization via bunch length tool
      * 5MeV emittance measurements
 3. Swing
      * Soak RF/Mag at design settings
      * 5MeV emittance measurements (cont)
      * Beam to Inj. Spectrometer
          o Measure/Set Energy
          o Measure Energy Spread


      1.4 2015-02-14 Sat

 1. Owl
      * Soak RF/Mag at design settings
      * soak all Magnets
      * beam in inline dump
 2. Day
      * Soak RF/Mag at design settings
      * Commission INJ sync light monitor
      * Measure/Set/Measure Inj Chicane M56
      * Inj. Energy spread via Inj SLM
      * emittance measurements in Injector chicane
          o Collect data for match
 3. Swing
      * Soak RF/Mag at design settings
      * Beam to Spectrometer
      * Bunch length measurements via back phasing (reference ATlis: 10684)
      * Repeat Energy Spread measurement at Spectrometer dump
      * Back to inline dump


      1.5 2015-02-15 Sun

 1. Owl
      * Soak RF/Mag at design settings
      * Beam to 1R
      * NL phasing
 2. Day
      * Load in Injector Match values
      * Measure Injector Emittance/TWISS
      * restore beam to 1R
      * ORFP
      * 1E emittance/TWISS measurements
          o Match calculated offline, to be loaded Tuesday Day shift
 3. Swing
      * SL phasing
      * Beam to 2R
      * ORFP


      1.6 2015-02-16 Mon

 1. Owl
      * Beam to 2R
      * ORFP
      * Arc1 M56 = 0
      * 2E emittance/TWISS measurement
          o Match calculated offline, to be loaded Tuesday Day shift
      * Extract 1-pass to BSY dump
 2. Day
      * 1-pass to BSY dump
      * Go CW!
      * Optimize Inj. bunching/phasing(0L04)
      * Bunch length measurement via Inj SLM
      * Bunch length measurement via Arc1 SLM
      * Energy Spread via Inj and Arc1 SLM
 3. Swing - BS
      * CW 1-pass to BSY Dump
      * RTI test at 2GeV, 125MHz rep. rate.
          o 50μ A max beam current
          o 125MHz rep.rate
          o bunch charge equivalent to 200μ A at 499MHz repetition rate
      * or lower machine to 1GeV per pass
          o 100μ A max beam current
          o 249.5MHz repetition rate
          o bunch charge equivalent to 200μ A at 499MHz repetition rate


      1.7 2015-02-17 Tue

 1. Owl - BS
      * RTI test
      * restore CEBAF to configuration energy
 2. Day
      * *Punch list, limited access AM*
      * restore CEBAF to configuration energy
      * load 1E and 2E match
      * beam back to 2R
 3. Swing
      * beam to 3R,4R
      * ORFP
      * ARC[1..3] M56 = 0
      * beam to 5R,6R
      * ORFP
      * ARC[4..5] M56 = 0


      1.8 2015-02-18 Wed

 1. Owl
      * beam to 7R, 8R
      * ORFP
      * Arc6 M56 = 0
      * beam to 9R, AR
      * ORFP
 2. Day
      * auto-quad test (Joyce)
      * beam to 5C dumplet
      * E[3..A,5C] emittance/TWISS measurements
          o match calculated offine.
 3. Swing
      * Magnetic 5-pass extraction to 1C dumplet
      * 1C (5-pass) emittance/TWISS measurement
      * Magnetic (or RF) 1-pass extraction to 2C dumplet


      1.9 2015-02-19 Thu

 1. Owl
      * Magnetic (or RF) 1-pass extraction to 2C dumplet
      * Skew search (part of ATlis: 14931
        <http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14931>)
      * 2C (1-pass) emittance/TWISS
 2. Day
      * *punch list, limited access AM*
      * load match values where appropriate
      * Beam back to 5C dumplet
      * ORFP check
      * ORFP second iteration
          o interleaved with quad centering
 3. Swing
      * Beam to 5C
      * ORFP w/ quad centering


      1.10 2015-02-20 Fri

 1. Owl
      * Beam to 5C
      * ORFP w/ quad centering
 2. Day
      * Beam to 5C
      * ORFP w/ quad centering
 3. Swing
      * Beam to 5C
      * ORFP w/ quad centering


      1.11 2015-02-21 Sat

 1. Owl
      * Beam to 5C
      * ORFP w/ quad centering
 2. Day
      * 5-pass to 1C dumplet
      * emittance/TWISS measurements again
      * 1-pass to 2C dumplet
      * emittance/TWISS measurements again
 3. Swing
      * RTI 2nd try?


      1.12 2015-02-22 Sun

 1. Owl
      * RTI 2nd try?
 2. Day
      * load 2C match values
      * load 1C match vales

Author: Arne Freyberger

Created: 2015-02-10 Tue 15:52

Emacs <http://www.gnu.org/software/emacs/> 24.3.1 (Org 
<http://orgmode.org> mode 8.0-pre)

Validate XHTML 1.0 <http://validator.w3.org/check?uri=referer>

-- 
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab
12000 Jefferson Avenue      Cell: (757) 876-6289
Postal Suite 19             Email:  freyberg at jlab.org
Newport News, VA 23606

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20150211/282fa54f/attachment-0002.html>


More information about the BTeam mailing list