Assuming JLAB is open for business tomorrow (there is a 4pm meeting on
this topic), the plan tomorrow will be:
1. Make a short access (6 to 7am'ish) into the NL to align the Inj.
Sync light camera and verify if the Yao cavity electronics are
installed.
2. Resume beam delivery:
1. Injector checkout: Gun Group followed by Inj group.
2. Get beam 1R or BSY dump
3. Optimized injector setup/bunch length
The full plan is below or on the MCC whiteboard:
Spring 2015 Startup Evolution
1 Spring 2015 StartUp OPS
1.1 Spreadsheet
* Run Spread Sheet
<https://docs.google.com/spreadsheets/d/1AMVnjOjYZAqxLSQI_bzgt4cbmZlRY0DIh6uUaYCadPk/pubhtml>
* Please send me your gmail address if you wish to have edit privileges
1.2 |[0/7]| Deferred tasks - DEFERRED not FORGOTTEN!
* |[ ]| Calibrate INJ sync light monitor (Freyberger)
o *deferred until after Inj. SLM is aligned*
* |[ ]| Inj. Energy spread via Inj SLM
o *deferred until after Inj. SLM is aligned*
* |[ ]| Repeat Energy Spread measurement at Spectrometer dump
o *deferred*
* |[ ]| re-measure Injector Emittance/TWISS
o *defer to after 0L04 phasing*
* |[ ]| Measure Inj. Chicane M56 (Krafft)
o *defer until Yao electronics are confirmed in the tunnel*
* |[ ]| Arc1 M56 = 0
o *deferred to later*
* |[ ]| 2E emittance/TWISS measurement
o Match calculated offline, to be loaded Tuesday Day shift
o *deferred to later*
1.3 |[1/5]| Maintenance Tasks
* |[ ]| Align INJ Sync. Light Monitor (Wednesday Morning)
* |[ ]| Verify Yao cavity electronics in tunnel (Wednesday Morning?)
* |[ ]| West Arc Power Loop configuration (4h)
* |[ ]| Resurrect 1L05
* |[X]| MARC6++ Water Flow–Acid Flush
1.4 2015-02-18 Wed
1. |[0/1]| Owl
* |[ ]| *Hot Standby*
* |[ ]| Prep for resumption of beam delivery
* |[ ]| Short controlled access into NL if Freeman/Freyberger in
early
o |[ ]| Inj. Sync. Light Alignment (Freeman)
o |[ ]| Verification of Yao cavity electronics installation
(Freyberger)
2. |[0/6]| Day
* |[ ]| Short controlled access into NL
o |[ ]| Inj. Sync. Light Alignment (Freeman)
o |[ ]| Verification of Yao cavity electronics installation
(Freyberger)
* |[ ]| Recover CEBAF
* |[ ]| Injector setup re-visited (4h?)
o |[ ]| Wien
o |[ ]| Everything else
* |[ ]| 1-pass to BSY dump (2h?)
* |[ ]| Go CW!
* |[ ]| Optimize Inj. bunching/phasing(0L04)
o Kazimi
o Tief
o Ahmad Mahmoud
3. |[0/3]| Swing
* |[ ]| CW 1-pass to BSY Dump
* |[ ]| Bunch length measurement via Inj SLM (optional)
* |[ ]| Bunch length measurement via Arc1 SLM
* |[ ]| Energy Spread via Inj and Arc1 SLM (optional, can be
performed at anytime)
* |[ ]| RTI test at 2GeV, 249.5MHz rep. rate.
o 50μ A avg. beam current
o 249.5MHz rep.rate
1.5 2015-02-19 Thu
1. |[0/1]| Owl - BS
* |[ ]| RTI test
2. |[0/4]| Day
* |[ ]| Acquire 2E ε and TWISS data
* |[ ]| Auto quad commissioning (Joyce)
* |[ ]| Pathlength Calculator Upgrade Com. (Joyce)
* |[ ]| Mya Save/Restore Commissioning (CJS)
* |[ ]| Auto steer commissioning (Joyce)
3. |[0/6]| Swing
* |[ ]| load 1E and 2E match
* |[ ]| beam back to 2R
* |[ ]| beam to 3R,4R
* |[ ]| ORFP
* |[ ]| ARC[1..3] M56 = 0
* |[ ]| beam to 5R,6R
* |[ ]| ORFP
* |[ ]| ARC[4..5] M56 = 0
Author: Arne Freyberger
Created: 2015-02-17 Tue 14:10
Emacs <http://www.gnu.org/software/emacs/> 24.3.1 (Org
<http://orgmode.org> mode 8.0-pre)
Validate XHTML 1.0 <http://validator.w3.org/check?uri=referer>
--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab
12000 Jefferson Avenue Cell: (757) 876-6289
Postal Suite 19 Email: freyberg at jlab.org
Newport News, VA 23606
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20150217/c022cf20/attachment-0002.html>
More information about the BTeam
mailing list