[BTeam] Afternoon Update
Arne Freyberger
freyberg at jlab.org
Thu Feb 19 15:15:31 EST 2015
Presently down hard with a chopper 1X amplifier failure. Otherwise, see
links below for details about today's activities.
1 Spring 2015 StartUp
1.1 Spreadsheet
* Run Spread Sheet
<https://docs.google.com/spreadsheets/d/1AMVnjOjYZAqxLSQI_bzgt4cbmZlRY0DIh6uUaYCadPk/pubhtml>
* Please send me your gmail address if you wish to have edit privileges
1.2 |[4/7]| Maintenance Tasks
* |[ ]| 1L22-8 LLRF Tuning issues 3321143
<https://logbooks.jlab.org/entry/3321143>
* |[ ]| West Arc Power Loop configuration (4h)
* |[ ]| Resurrect 1L05
* |[X]| Align INJ Sync. Light Monitor (Thursday Morning)
* |[X]| Verify Yao cavity electronics in tunnel (Thursday Morning?)
* |[X]| MARC6++ Water Flow–Acid Flush
* |[X]| RSEP9A Acid flush
1.3 2015-02-18 Wed
1. |[2/4]| Swing
* |[X]| Injector setup re-visited (4h?)
o |[X]| Gun Group
o |[X]| Inj Group
* |[X]| Optimize Inj. bunching/phasing(0L04)
o Kazimi/Wang/Hofler
* [!] CW 1-pass to BSY Dump, 2nd attempt.
o did not happen
1.4 2015-02-19 Thu
1. |[1/1]| Owl
* |[X]| ORFP to 5C dumplet
2. |[2/6]| Day
* |[X]| Access into North Linac
o |[X]| Laser Table alignment 3321136
<https://logbooks.jlab.org/entry/3321136> 3321169
<https://logbooks.jlab.org/entry/3321169>
o |[X]| Inj. Sync Light alignment 3321126
<https://logbooks.jlab.org/entry/3321126>
o |[X]| YAO cavity electronics check 3321131
<https://logbooks.jlab.org/entry/3321131>
o |[X]| RSEP9A Acid flush
o |[X]| Replace Lambertson camera 3321090
<https://logbooks.jlab.org/entry/3321090>
o |[X]| AR dumplet retraction/limit switch issue 3321114
<https://logbooks.jlab.org/entry/3321114>
o |[X]| MQK7S10 investigation 3321123
<https://logbooks.jlab.org/entry/3321123>
o |[X]| RADCON retrieval of SL instrumentation
* |[X]| Mya Save/Restore Commissioning (CJS)
* |[ ]| Replace failed chopper-1X amplifier
* |[ ]| Auto quad commissioning (Joyce)
* |[ ]| Resume ORFP
3. |[0/6]| Swing
* |[ ]| Continue ORFP to 5C dumplet
o Verify M56=0 in Arc[1..5]
1.5 2015-02-20 Fri
1. |[0/5]| Owl
* |[ ]| beam to 7R, 8R
* |[ ]| ORFP
* |[ ]| beam to 9R, AR
* |[ ]| ORFP
* |[ ]| beam to 5C dumplet
2. |[0/5]| Day
* |[ ]| MO/Pathlength evaluation and decision
* |[ ]| Adjust MO frequency or not
* |[ ]| 1-pass beam to BSY dump
* |[ ]| Go CW!
* |[ ]| Inj. Optimization with 1-pass beam
3. |[0/6]| Swing
* |[ ]| Bunch length measurement in NL/ARC1
* |[ ]| Bunch length measurement at Inj. Spectrometer Dump
* |[ ]| E[1..A,5C] emittance/TWISS measurements
o match calculated offine.
* |[ ]| Magnetic 5-pass extraction to 1C dumplet
* |[ ]| 1C (5-pass) emittance/TWISS measurement
* |[ ]| Magnetic (or RF) 1-pass extraction to 2C dumplet
Author: Arne Freyberger
Created: 2015-02-19 Thu 15:12
Emacs <http://www.gnu.org/software/emacs/> 24.3.1 (Org
<http://orgmode.org> mode 8.0-pre)
Validate XHTML 1.0 <http://validator.w3.org/check?uri=referer>
--
Arne Freyberger
Director of Accelerator Operations
Jefferson Lab
12000 Jefferson Avenue Cell: (757) 876-6289
Postal Suite 19 Email: freyberg at jlab.org
Newport News, VA 23606
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20150219/7a57ae50/attachment-0002.html>
More information about the BTeam
mailing list