[BTeam] Updated Schedule Posted
Brian Freeman
bfreeman at jlab.org
Tue Oct 29 09:59:50 EDT 2019
All,
Gantt chart and task list updated to:
http://opsweb/gantt/2019_Fall/fall2019Run-chart.html
and
http://opsweb/gantt/2019_Fall/fall2019Run-tasks.html
Quick update .....
Last week we obtained beam authorization to run to the In Line Dump. Injector setup is well under way, and many tasks have been marked as complete. Today investigation continues on possible charging viewer that maybe changing the beam orbit.
SRF is continuing to commission 1L20 and 1L25 modules, nothing on 1L07 as of yet (as far as I know, tuner cables completed yesterday?).
Much of the SL RF has been on, and EES-RF working the issues as they are found. Injector and up to Zone 17 in NL has been on as well. With the exception of 1L12 and 1L07. EES-RF also lost 1L13 transformer and must replace it. No shortage of work for these folks!
DC Power completed Hi potting and and shunt resistor checks. Doglegs and XSEPT magnets ramped up. HCO on the 20 amp and 10 Amp trims also underway.
Things are progressing well.
Does anybody know of any show stoppers?
What is missing from the Task list?
Thanks,
-Brian
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20191029/8ecd5b77/attachment-0001.html>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: fall2019Run.mpx
Type: application/vnd.ms-project
Size: 15022 bytes
Desc: fall2019Run.mpx
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20191029/8ecd5b77/attachment-0001.mpp>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: fall2019Run.pdf
Type: application/pdf
Size: 184853 bytes
Desc: fall2019Run.pdf
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20191029/8ecd5b77/attachment-0001.pdf>
More information about the BTeam
mailing list