[BTeam] One-day delay in beam return to Hall C
Matthew Bickley
bickley at jlab.org
Wed Mar 18 13:52:40 EDT 2020
BTeam members,
Due to a target installation delay in Hall C we won't be sending beam there until Saturday day shift at the earliest, not Friday swing shift as we had hoped. Therefore we won't learn about the impact on Hall C beam from the gun seed laser swap happening tomorrow until Saturday evening. We should plan to have our discussion about next steps following the swap either on Sunday or first thing Monday.
Matt