[BTeam] Tuesday beam studies 9/15
Jay Benesch
benesch at jlab.org
Wed Sep 9 14:20:43 EDT 2020
Reza and colleagues,
I told the morning and 1330 meetings that we would be taking a full
eight hours next Tuesday, likely starting at 0900. Test plan order
needs to be decided. Hall C would like an hour access, not compatible
with Smart Alarm test plan or BNNT test plan. Dennis's RayTrace test
plan is compatible.
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21000 RayTrace 1.5 hr
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21151 Smart Alarm 4 hr
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21234 BNNT 2 hr
Suggested order:
RayTrace so RadCon can support Hall C entry during normal hours.
restore CW through empty target to Hall C
Smart Alarm
BNNT Can this be parasitic during tune beam portion of Smart Alarm?
If this falls off the table due to over-run of the two above, we
simply continue with existing viewer flags.
Begin restoration to all halls at 1630, after swing crew turn-over.
Attempt to complete by 1700, eight hours after start.
Jay