[BTeam] Reschedule: Tuesday beam studies 9/15
Michael Tiefenback
tiefen at jlab.org
Fri Sep 11 08:18:27 EDT 2020
Our viewer supports have not been designed to support any heat load. I raise the question: Does CW on the BNNT flag result in heating which might have unpleasant consequences? It seems to me that placing a BNNT flag into a more readily tended piece of beam line than Arc 7A would be better than potentially dirtying up ITV7A09. An issue for discussion rather than a forecast of disaster.
I left the Bteam in the reply list in case others want to contribute to the discussion.
Michael Tiefenback
________________________________
From: BTeam <bteam-bounces at jlab.org> on behalf of Jay Benesch <benesch at jlab.org>
Sent: Thursday, September 10, 2020 16:36
To: Reza Kazimi <kazimi at jlab.org>
Cc: bteam at jlab.org <bteam at jlab.org>
Subject: [BTeam] Reschedule: Tuesday beam studies 9/15
Colleagues,
Given that the safety briefing is Tuesday, I will propose to the RCs tomorrow that the beam studies be done Monday.
It has been suggested that the BNNT viewer be re-classified in CED as CW and subjected to 30 uA CW just before Hall C switches to first pass. This would be in lieu of tune beam Monday. Comments?
Jay
________________________________________
From: Jay Benesch <benesch at jlab.org>
Sent: Wednesday, September 9, 2020 2:20 PM
To: Reza Kazimi
Cc: bteam at jlab.org
Subject: Tuesday beam studies 9/15
Reza and colleagues,
I told the morning and 1330 meetings that we would be taking a full
eight hours next Tuesday, likely starting at 0900. Test plan order
needs to be decided. Hall C would like an hour access, not compatible
with Smart Alarm test plan or BNNT test plan. Dennis's RayTrace test
plan is compatible.
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21000 RayTrace 1.5 hr
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21151 Smart Alarm 4 hr
http://opsweb.acc.jlab.org/CSUEApps/atlis/task/21234 BNNT 2 hr
Suggested order:
RayTrace so RadCon can support Hall C entry during normal hours.
restore CW through empty target to Hall C
Smart Alarm
BNNT Can this be parasitic during tune beam portion of Smart Alarm?
If this falls off the table due to over-run of the two above, we
simply continue with existing viewer flags.
Begin restoration to all halls at 1630, after swing crew turn-over.
Attempt to complete by 1700, eight hours after start.
Jay
_______________________________________________
BTeam mailing list
BTeam at jlab.org
https://mailman.jlab.org/mailman/listinfo/bteam
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20200911/54c4dcb8/attachment-0001.html>
More information about the BTeam
mailing list