[BTeam] testplans schedule for tomorrow, 11/07 and 11/14
Yves Roblin
roblin at jlab.org
Tue Oct 31 15:48:11 EDT 2023
Tomorrow:
ATLIS 110183 BEM 8.0 preinstallation checkout, please do first around 830.
ATLIS 110163 Wien filter coupling study. up to 4hours.
After completion, Yan will come in and do the Wien filter change to -15.3 degrees, checkout the injector and restore beam.
Nov 7th (exact time to be coordinated with hall but current thinking is to start around midnight.)
FFB Hall A fast feedback restoration . estimate of 4 hours. Its first priority. ATLIS 110062
aperture scan study ATLIS 22722 (4 hours)
Maintenance day starts at 800am.
Nov 14th:
Hall A BCM resolution study with 2Khz helicity flip. 109569 ( 2hours)
Another FFB test if necessary.