[BTeam] schedule for tomorrow maintenance day and next week Beam study
Yves Roblin
roblin at jlab.org
Tue Mar 12 15:05:30 EDT 2024
Tomorrow morning, during maintenance day.
stop beam 700am, surveys, etc..
open up 830am (linacs)
as soon as injector is open:
Joe Wilson for 30 minutes walkthrough.
After this, we lock up injector and Joe Grames does weekly surface charge measurement 15 minutes : https://tasklists.jlab.org/bslist/tasks/111106
Followed by https://tasklists.jlab.org/bslist/tasks/111261<https://tasklists.jlab.org/bslist/tasks/111261> (3-4 hours)
At 1230pm we expect to have people out of the tunnels and start locking up.
Beam back to physics by 6pm. During restore, do rf recovery/phasing if needed, orbits, machine checks, take a fopt.
for next week beam studies (3/20)
MOMOD test (1-2 hours) need CW to HALLC 3 pass. Do this first, ask Hall C to stay locked up to give us a termination point.
then:
BLM tests (finishing that 8hours testplan, we expect 2 hours) https://tasklists.jlab.org/bslist/tasks/107920
Yag viewer calibration in injector 3 hours https://tasklists.jlab.org/bslist/tasks/24275
followed by 2-3 hours of machine checks/recovery
Send me corrections/suggestions if I missed or mistated anything.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/bteam/attachments/20240312/dad0c147/attachment.html>
More information about the BTeam
mailing list