Dear All,
 The bubble chamber is being installed right now in CEBAF injector. The run starts on Thursday May 10th at 4:00 pm and runs 27/7 till Friday May 18, 8:00 am.
 The safety documents for this run are here:
 https://wiki.jlab.org/ciswiki/index.php/Bubble_Chamber_Reviews
 Please read the TOSP (https://wiki.jlab.org/ciswiki/images/b/b7/Operational_safety_procedure_form_75428.pdf) and sign the hardcopy left in MCC.
 We are having a daily meeting in MCC at 8:15 am to discuss plans, please attend.
 Details about this test (run plan, updates) will be posted to the wiki:
 https://wiki.jlab.org/ciswiki/index.php/Bubble_Chamber_Beam_Test_May_2018
 I am also preparing the shift schedule, please plan to take shifts.
 Thank you very much.
Riad.
 
    
    