Since I have new PMT monitoring timeline tools not available for pass1 I won’t have the full picture until a new pass0 (unless there are some surviving pass0 mon files).  However I don’t anticipate any energy re-calibrations for pass2.  The new timing calibration procedures are now in place and can be done following the FTOF schedule.  

Cole

> On Nov 16, 2022, at 10:34 AM, silvia--- via Clas12_calcom <clas12_calcom at jlab.org> wrote:
> 
> Dear detector experts,
> apologies for being pushy, please don't forget that I need your feedback
> to prepare the ready for calibration review of this coming Friday - see
> email here below.
> Thank you!
> Best regards,
> Silvia
> 
> 
>> Dear all,
>> this coming Friday (November 18th) there will be the "ready for
>> calibration" review of RGB Fall19/Spring20, in order to officially start
>> the recalibration for the pass2 of the last two pieces of RGB.
>> The charge is unchanged since the previous review:
>> 1) Overview of the dataset
>> 2) Run Group leadership, responsibilities , manpower
>> 3) Recalibration effort: number of runs to calibrate for each subsystem
>> with their applicable run ranges ( based on the work for the pass 1
>> calibration)
>> 4) Overview of the list of production and calibration runs to be included
>> in the calibration timelines
>> 5) Detailing of known problems during any of the production/calibration
>> runs that affect the calibration quality
>> 6) Detector subsystem calibration QA specs
>> 7) Recalibration timeline (2 month window ) with trackable milestones
>> leading up to the pass 2 ready for cooking review
>> 
>> I need the feedback of all detector contacts to address points 3), 5), 6)
>> and 7). For points 6) and 7), please see the slides at
>> https://urldefense.proofpoint.com/v2/url?u=https-3A__box.in2p3.fr_index.php_s_tBBs3gNnecGsFdG&d=DwIFaQ&c=CJqEzB1piLOyyvZjb8YUQw&r=qEkdYeiAbIsODpxTO59E_ab70KWmehf8Tr3XybSYmSs&m=t7m5KH0VVNfdj6a1T3agRzCURiQNPHfCKUrwGfBXp5qXA6AeA14H66-fQypldjbo&s=1h89SbIpI-kE-6F8pmd3xhiFFgLRg2Ou9lazFNSl99M&e=  (the ones I made for
>> the S19 ready-for-calibration review) and tell me if you think anything
>> has changed.
>> 
>> I would need all this by Wednesday evening, if possible. Please get in
>> touch with me for more details or if there is any need to
>> discuss/exchange.
>> 
>> Thanks a lot!
>> Best regards,
>> Silvia
>> 
>> 
> 
> 
> _______________________________________________
> Clas12_calcom mailing list
> Clas12_calcom at jlab.org
> https://mailman.jlab.org/mailman/listinfo/clas12_calcom




More information about the Clas12_calcom mailing list