[Clas12_calcom] [EXTERNAL] new pass0.7 RG-M timelines

Justin Brian Estee esteejus at mit.edu
Thu Sep 29 13:50:49 EDT 2022


Dear All,


RG-M has produced the latest pass0.7 which includes the following changes:

  1.  ??Final DC alignment & T0 offset for zero-field run

Please take a look at the timelines below, specifically concerning the DC and FTOF timelines which will be the next calibration stage after the beam-offset calibrations.

https://clas12mon.jlab.org/rgm/pass0.7/tlsummary/
https://clas12mon.jlab.org/rgm/pass0.7_qa/tlsummary/

I will complete the beam-offset calibrations and the remaining alignments, and I hope to have a new pass0.8 produced in one week ready for the next calibration task (DC/FTOF which ever we decide after discussion). Let me know if you have any issues with the timelines.

Best regards,
Justin
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/clas12_calcom/attachments/20220929/f3062fe0/attachment.html>


More information about the Clas12_calcom mailing list