[Clas12_calcom] [EXTERNAL] RGA Sp18 v0_24 timeline available

Timothy Hayward haywardt at mit.edu
Tue Feb 11 14:47:09 EST 2025


Dear CALCOM,

I have emailed the subsystem experts directly but also wanted to send out a formal email to the mailing list. The potential final full timelines for RGA Sp18 using cj 11.1.0 and following all calibration efforts are available here<https://clas12mon.jlab.org/rga/pass2/sp18/pass0/sp18_v0.24/tlsummary/>. Please have a look at your relevant subsystem and let me know your thoughts on the final calibrations. There are certainly a few runs here and there that appear outside the formal qa lines but that can possibly be attributed to poor fits, special settings, etc.

Thank you very much for your help,
Timothy