Dear All,
we have good news from the magnet group: the heater replacement was successful and the torus is again operational.
Presently the machine is still down for maintenance that will continue for the day shift. As part of the planned work, the injector group will set the Wien angle to the optimal value that was determined based on yesterday spin dance results and, when we will get beam, we will do final Moller runs to check the new setting. We will then go back to production.
There will be a RC meeting in the Counting House today at 2:30pm to review the status and run plan.
Best regards,
	Raffaella