[Clas12_rich] RICH assembly in October
Walt Akers / JLAB
akers at jlab.org
Thu Aug 4 09:35:52 EDT 2016
Dear Tyler:
I've made quite a bit of progress in modeling this space issue, however,
the process has revealed some existing issues that will need to be worked
around. I'm putting together a plan now that should allow the RICH work
to continue on the original schedule - albeit with a somewhat different
space layout. I'll send that information out as soon as it is complete and
has been vetted by Stepan, Volker and Patrizia to make sure that it reflects
reality and can satisfy everyone's requirements.
Please proceed with the expectation that this work can be performed as
scheduled.
Walt
Tyler Lemon wrote:
> Dear Walt,
>
> Has there been any progress on the model for EEL 124 cleanroom layout
> you mentioned in your email on July 26? We want to be sure that there
> will be enough space to accommodate the installation of the RICH
> assembly structure and the assembly and testing of the RICH.
>
> Best regards,
> Tyler
>
> ------------------------------------------------------------------------
> *From: *"Walt Akers / JLAB" <akers at jlab.org>
> *To: *"Tyler Lemon" <tlemon at jlab.org>, "Saptarshi Mandal"
> <mandal at jlab.org>, "Stepan Stepanyan" <stepanya at jlab.org>, "Stephan
> Aune" <saune at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "Franck
> Sabatie" <sabatie at jlab.org>, "Volker Burkert" <burkert at jlab.org>,
> "Latifa Elouadrhiri" <latifa at jlab.org>, "clas12 rich"
> <clas12_rich at jlab.org>, "Yuri Gotra" <gotra at jlab.org>
> *Cc: *"Patrizia Rossi" <rossi at jlab.org>
> *Sent: *Tuesday, July 26, 2016 9:46:07 AM
> *Subject: *Re: RICH assembly in October
>
> Tyler:
>
> I've received an SVT model from Saptarshi and am working
> to merge the two workplans now. I'll send a model when it is
> complete.
>
> Walt
>
> Tyler Lemon wrote:
> >
> > Hi Saptarshi,
> >
> > With respect to the schedule shared yesterday, we were informed that
> > the assembly and structural components of the RICH will arrive in
> > October. Because of this, we are hoping to to set up the assembly and
> > testing area in EEL 124 as soon as possible. I trust your design will
> > accommodate for the installation of the assembly structure and also
> > the assembly and testing of the RICH. Also, could you send the design
> > for the layout of EEL 124 to the clas12_rich mailing list when it is
> > done? Thank you in advance.
> >
> > Best regards,
> >
> > Tyler
> >
> >
More information about the Clas12_rich