So... just for clarification. Is there a reason why entering through
the backdoor of the cleanroom is preferred. I only ask because using
that entrance actually forces us to leave much space unused in the front
of EEL 125 in order to accommodate the movement of material in and
out. This would impact the overall usability of both rooms for more
than 6 months.
Thanks for the information,
Walt
Tyler Lemon wrote:
> Dear Marco Contalbrigo and Marco Mirazita,
>
> We have looked at the video that Walt sent this weekend and have a few
> questions and comments. Attached is a screen shot of the final EEL 124
> layout for reference.
>
> From Walt's video and schedule, we would have to wait until at least
> mid-January to begin RICH assembly because of SVT and MicroMegas
> movement. It would be nice if the Forward Tagger could move to a
> different area of EEL 125 (maybe the corner where the HPS equipment
> is) because this would free up the back roll-up door and allow the SVT
> and MicroMegas to enter the clean room through that door. This in turn
> would allow RICH to independently be assembled regardless of SVT and
> MicroMegas movements. For this to happen, could the HPS equipment move
> to a different location and could the Forward Tagger be moved to a
> different area of EEL 125? Amanda has contacted Marco Battaglieri
> regarding the Forward Tagger to see if it can be moved.
>
> Also just for information, the door that the assembled RICH would go
> through is 15.75 feet wide. Would this be adequate space for RICH to
> pass though?
>