Hi Marc,
I am on vacation till the end of the next week.
There is some space in the racks on the third level of the forward carriage. There are two racks on each side of the beam with Caen HV power supplies and distribution boxes. Top part of these racks is not occupied yet.
I think it would be a good place if Sergey agrees.
-Eugene
----- Original Message -----
> From: "Marc McMullen" <mcmullen at jlab.org>
> To: "Eugene Pasyuk" <pasyuk at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "clas12 rich" <clas12_rich at jlab.org>,
> "dsg-internal" <dsg-internal at jlab.org>, "Doug Tilles" <tilles at jlab.org>, "Denny Insley" <dinsley at jlab.org>
> Cc: "Patrizia Rossi" <rossi at jlab.org>
> Sent: Thursday, July 14, 2016 7:16:57 AM
> Subject: RICH detector slow controls location
> Hi Eugene,
>
> I would like to meet in the hall to discuss the location of the slow
> controls equipment for the RICH detector on the forward carriage. The
> DSG would require about 18U (~32") total of rack. This should give
> enough space to install the equipment.
>
> I will be heading over to the hall this morning (8am) to have a look at
> the area, if there is a time this morning which is good for you please
> let me know.
>
> Regards,
>
>
>
> --
> Marc McMullen