[Cuga] PAC35 Call for Proposals: 12 GeV Science---a message from Larry Cardman

Rachel Harris harris at jlab.org
Fri Oct 9 11:13:24 EDT 2009


  PAC 35 CALL FOR PROPOSALS: 12 GeV SCIENCE


      October 9, 2009

Dear Jefferson Lab Users,

PAC35 will continue the annual call for proposals for 12 GeV science and 
user commitments to the construction of experimental apparatus that 
began with PAC30. Once again, our main focus will be on the detailed 
consideration of proposals and letters of intent for the science that 
will be appropriate for the first five years of running with the Upgrade 
using the base equipment and modest scale ancillary apparatus. PAC35 
will have as a primary focus experiments to be done in the 12 GeV era 
with the full range of energies that will be available and the “base 
equipment” planned as part of the Upgrade project. In view of the number 
of experiments that have already been recommended for approval by PACs 
30, 32 and 34, for this PAC the criterion for recommendation for 
approval will be that the proposal represents “high quality physics 
that, based on what we know today, is highly likely to be of sufficient 
scientific merit that it will be included in /the top half of/ the 
priority list to be established for the first 5 years of 12 GeV operations.”

The charge to PAC35 will also include two elements added at PAC34. The 
first will be to provide advice on the scientific merit, technical 
feasibility and resource requirements for new proposals for experiments 
whose execution will require major instrumentation /not/ included in the 
formal scope of the 12 GeV Upgrade. For such proposals, the PAC will be 
asked to identify science that it considers as effective a use of 
resources as the research programs that will be supported by the “base 
equipment” under construction for the 12 GeV Upgrade and appropriate for 
the first decade of 12 GeV operation. The second additional charge will 
be to provide advice on the execution (since PAC34) and plans for 
completion of the plan that has been developed for running the remainder 
of the “6 GeV program” between now and the final shutdown for the 
conversion of CEBAF to 12 GeV. We will continue to seek, in particular, 
the PAC’s advice on how to deal with cuts in the total program that may 
be necessary in the all-too-likely event that funding levels over the 
next few years do not permit equipment construction and operation of the 
accelerator at the 80% of optimum level foreseen in the draft schedule.

*PAC35 will be held during the week that begins January 25. Proposals 
for PAC 35 are due at Jefferson Lab by the close of business on Monday, 
December 14, 2008. *In this Call for Proposals, we discuss each of the 
elements of the PAC35 charge in turn.

*I. **Proposals and Letters of Intent for Experiments that Will Use the 
Base Equipment (and modest scale ancillary equipment):*

With the first year of the formal (post CD-3) construction of the 12 GeV 
Upgrade (CD-3) having just been completed and the first of the annual 
progress reviews having taken placeit is more important than ever that 
we complete the identification of intended contributions of the 
Jefferson Lab user community to the construction of the “base equipment” 
experimental apparatus that will be constructed as part of the Upgrade 
project. As has been the case at previous PACs reviewing proposals of 
this type, the following “rules” must be followed:

As part of the proposal, the proposing scientists and institutions must state clearly their intention to participate in and contribute to the construction of that base equipment.  Commitments made as part of proposals to PAC30, PAC32, and/or PAC34 may be included as part of the commitments identified for PAC35 proposals, but each new proposal must include the following items:

>From groups that made commitments toward the base equipment construction in proposals accepted by PAC30, PAC32 or PAC34:

·         A re-affirmation of their previously stated intention to participate in and contribute to the construction of the base equipment, along with a brief description of progress toward realizing that commitment (signed memoranda of understanding, progress toward obtaining funding and/or carrying out work relevant to fulfilling that commitment, such as design studies, R&D efforts, prototyping, etc. aimed at the realization of some part(s) of the base equipment), and/or

·         A clear statement of any new incremental commitment toward the base equipment construction.

>From each group that did not make a commitment toward the base equipment construction in a proposal accepted by PAC30, PAC32 or PAC34:

·         A clear statement by the proposing scientists and institutions of their intention to participate in and contribute to the construction of that base equipment, outlining the planned effort and responsibilities to be undertaken.

Note that the base equipment includes all devices included explicitly in the 12 GeV Upgrade Project Design Solution Documents (DSDs) which can be found on the JLab 12 GeV Technical Scope webpage (http://www.jlab.org/12GeV/index.html#DSD).   

This “category” of proposals may include use of existing ancillary equipment, and we will accommodate such proposals /so long as the modifications needed are modest and the proposing scientists will undertake the funding and realization of those modifications in addition to their contributions to the base equipment construction.  /If you have questions about whether your proposal for this PAC should be considered under the “base equipment proposal” guidelines above or the “major new apparatus” guidelines below, please contact Larry Cardman directly.

As was the case at PACs 30, 32 and 34, we will give more serious 
consideration than usual to letters of intent for experiments using the 
“base equipment” that are submitted to this PAC so long as they are 
relatively well developed scientifically and the intended contributions 
of the proposers to the construction of the base equipment are clearly 
identified. A letter of intent that receives a strong endorsement by 
PAC35 will be treated in a manner analogous to how deferred proposals 
have been treated traditionally – i.e. it will have established a claim 
on the physics measurement but must be upgraded to an approved proposal 
by resubmission to the PAC as a full proposal within two PACs. Note that 
we are planning only one PAC per year, so this means the “rights” of a 
recommended Letter of Intent will last 1½ to 2 years (depending on the 
decision about the timing of the next PAC).

*II. **Proposals and Letters of Intent for Experiments that Will Require 
Major New Experimental Apparatus Not Included in the 12 GeV Upgrade 
Complement of “Base Equipment”:*

*This will be the second PAC that will consider proposals for apparatus 
that is not part of the “Base Equipment”. The proposers must understand 
that a positive recommendation from the PAC about the scientific merits 
of such a proposal will **only be the first step toward a final decision 
about their execution. Subsequent steps will include detailed technical 
reviews, the development of funding to support the construction, and the 
establishment of a “project” framework for its construction and 
installation. The laboratory’s formal commitment to the overall effort 
will come in the form of a written decision taken by the director. *

For proposals requiring the construction of major new apparatus, the 
proposing scientists and institutions must state clearly their intention 
to participate in and contribute to the construction of that apparatus. 
Each new proposal of this type must include the following items:

·         From each group of proposing scientists and institutions:

o   a clear statement of their intention to participate in and contribute to the construction of the new equipment

o   a summary of the responsibilities they will undertake as part of the construction effort, and

o   the identification of financial and human resources now available to them in support of the effort, and 

·         The proposal must also include summary statements identifying:

o   Resources that will be requested from JLab as part of the construction effort, and

o   a strategy to obtain the resources necessary to cover the entire construction and installation effort.

As is the case for letters of intent using the base equipment, we will 
give more serious consideration than usual to letters of intent for 
experiments involving the construction of major new apparatus at this 
PAC so long as they are relatively well developed scientifically and the 
intended contributions of the proposers to the construction of the base 
equipment are clearly identified. A letter of intent that receives a 
strong endorsement by PAC35 will be treated in a manner analogous to how 
deferred proposals have been treated traditionally – i.e. it will have 
established a claim on the physics measurement but must be upgraded to 
an approved proposal by resubmission to the PAC as a full proposal 
within two PACs. Note that we are planning only one PAC per year, so 
this means the “rights” of a recommended Letter of Intent will last 1½ 
to 2 years (depending on the decision about the timing of the next PAC).

*III. **PAC35 review of the execution (since PAC34) and plans for 
completion of the plan that has been assembled for running the remainder 
of the “6 GeV program” between now and the final shutdown for the 
conversion of CEBAF to 12 GeV.*

By the date of the PAC35 meeting, we will have completed the first year 
of execution of the draft plan that was developed (and reviewed at 
PAC34) for the execution of the remaining 6 GeV Science program. PAC35 
will be asked to comment on the progress of the science this effort 
represents, and on the compromises that were forced on us by the failure 
of the SANE target. Further, following the review of PAC34, the draft 
long range schedule was posted. It represents our goal for the science 
program between now and the final 6 GeV shutdown. As was noted at PAC34 
(and in many other venues), the execution of the full schedule as posted 
will require many things to “fall right”. Most specifically, it is based 
on the laboratory receiving sufficient funding to operate at ~80% of 
optimum utilization in the period between now and the shutdown, and the 
availability of equipment funding for some of the (as yet unbuilt) major 
apparatus needed for the program. As indicated at PAC34, we will 
continue to ask the PAC for advice on how to deal with cuts in the total 
program that may be necessary in the all-too-likely event that funding 
levels over the next few years do not permit equipment construction and 
operation of the accelerator at the 80% of optimum level foreseen in the 
draft schedule.

PAC35 will be held during the week that begins January 25. *Proposals 
for PAC 35 are due at Jefferson Lab by the close of business on Monday, 
December 14, 2009.* As is the established tradition, the JLab Technical 
Advisory Committee (TAC) will make comments on the technical viability 
of the proposals and provide these comments to the spokespersons and the 
PAC prior to the meeting. As always, proposals will be judged on the 
quality of the physics, technical feasibility, and the ability of the 
group to carry out the proposed measurements.

The PAC will not have a specific allocation of beamtime. It is our 
intent that the PAC process over the next five years will identify the 
initial physics program for the upgrade. The PAC will be requested to 
determine whether the proposals presented identify physics that in their 
opinion belongs in the first five years. The scientific prioritization 
of approved 12 GeV proposals and the development of the “run plan” for 
the first year of physics in each hall will begin about two years before 
the start of 12 GeV physics.


  Jeopardy

Jeopardy is irrelevant at this PAC as we are considering the 6 GeV 
program “frozen” and the 12 GeV program is at too early a stage to 
consider the jeopardy process. Assuming we follow the same procedures 
that were used with the startup of the original program using CEBAF, 
jeopardy reviews will begin three years after the start of physics in 
each hall.

*_GUIDELINES FOR PROPOSALS FOR PAC35_*


  New Proposals

New proposals requiring any beam energies that will be available with 
the Upgrade, including beam energies up to 12 GeV (for Hall D, and 11 
GeV for Halls A, B and C) will be reviewed by PAC 35. It is highly 
recommended that you consider the guidelines below (developed for the 
“standard” PAC proposals) when preparing your proposal:

1. Be careful to submit a complete package that can stand alone. Do not 
assume that the PAC is aware of information contained in previous 
proposals, technical notes, and letters of intent. If this information 
is important background for your proposal, be sure that you include it 
in the proposal, for example as an appendix.

2. Give justification for the uncertainty of the final results. Give 
realistic estimates of uncertainties in resolution, absolute momentum 
and angle calibrations, random coincidences rates, etc. and indicate how 
these impact the final results.

3. Be sure to include a detailed table showing how you calculated the 
number of days requested. Since run time is a very scarce resource, the 
PAC reviews very carefully the details of the request, makes its own 
calculation, and allocates the time accordingly. Therefore it is 
essential to give a full and detailed justification of your request.

4. Include experimental details and simulations. Complex and challenging 
experiments often require extensive justification and simulation 
calculations. Discussions of yield, backgrounds,accidentals, and 
projected statistical and systematic errors, are essential elements in 
the justification. To support these, it is important to give the results 
of simulation calculations that should be the basis of the experimental 
design. This is an essential component of the package required in order 
to get such proposals approved.

5. Indicate how the project relates to other approved 12 GeV proposals 
and/or proposals still “on the books” for the 6 GeV program. The PAC and 
the Laboratory have specifically asked proponents of new proposals to 
clearly state how their experimental goals are addressed by other 
approved experiments at the Laboratory. As stated in earlier PAC 
reports, failure to pay sufficient attention to this charge can result 
in the PAC not considering the new proposal until the information is 
provided.

*_Experiments with Similar Physics Goals _*

On your proposal cover sheet indicate any existing approved, 
conditionally approved, or deferred experiments that have physics goals 
similar to those in your proposal. In the text of your proposal, compare 
and contrast your proposal with respect to these proposals and 
experiments already considered or under consideration by previous PACs. 
Note that both one-page summaries and the full text for most proposals 
are available on-line at http://www.jlab.org/exp_prog/experiments/. You 
may also contact User Liaison (see below) for copies of proposals.

The spokespersons for the experiments and proposals you have listed on 
your proposal cover sheet will receive copies of your proposal prior to 
the PAC meeting. They will be allowed to submit written comments that 
will then be passed on to the PAC with a copy provided to you. If you 
fail to identify a previously approved proposal with similar physics 
goals, the spokesperson for the previously approved proposal may request 
that final approval of your proposal be contingent on review by a 
subsequent PAC of the issues they want raised. If laboratory management 
agrees that the request has merit, the final approval of your proposal 
will be deferred until the following PAC has reviewed the situation.


  Experiment Summaries

A summary of all approved and conditionally approved experiments can be 
found on line at: http://www.jlab.org/exp_prog/PACpage/Expsum.pdf. PAC 
reports can be found on line at: 
http://www.jlab.org/exp_prog/PACpage/pac.html.


  Beam Time

The beam time request should be provided in some detail using the 
standard forms identified below. Do not request any contingency time as 
the scheduling process includes this time. The beam requirements and 
time request should include all of the time for the following 
activities: setup & installation; alignment; calibration; check out and 
testing without beam; commissioning with beam; physics measurements 
(list all currents, energies, targets target and experimental apparatus 
configuration changes, and [for Halls A and C] spectrometer angle 
changes); and decommissioning.


  Letters-of-Intent

Letters-of-intent may be submitted to solicit the evaluation by the PAC 
of a new line of research before investing the large effort required to 
prepare a full proposal. Letters-of-intent will be made public after 
receiving PAC appraisal in the same manner as full proposals. For PAC35, 
contrary to tradition, we will allow serious letters of intent that 
identify physics that the PAC strongly encourages to “stake out” 
territory for the science program for two 12 GeV PAC cycles. With PAC 
recommendation for strong encouragement, we will treat such letters of 
intent in a manner similar to how we have traditionally treated deferred 
proposals submitted to the PAC (to remind you, deferred proposals must 
be resubmitted as a revised proposal to a future PAC. The revised 
proposal must address the issues and concerns raised by the PAC. A 
deferred proposal has established a claim to a physics measurement, but 
must be updated within two PACs, which will correspond to either 1½ or 2 
years, depending on the date chosen for PAC35.


  Due Date: New Proposals and Letters-of-Intent

Proposals, Updates, and Letters-of-Intent for PAC35 are due at the JLab 
User Liaison Office by close of business Monday, December 14, 2009*. *

Jefferson Lab

User Liaison Office

12000 Jefferson Avenue, Suite 5

Newport News, Virginia 23606

users at jlab.org


  Submissions

All submissions can be mailed or submitted electronically; electronic 
submissions are preferred. An electronic version must accompany all hard 
copies. Fax submissions are not acceptable.

All proposals and updates to be considered by PAC 35 must also include a 
completed:

Cover Sheet

Beam Time and Requirements List

These forms are available at the url: 
http://www.jlab.org/exp_prog/PACpage/PAC35/PACinfo.html 
<http://www.jlab.org/exp_prog/PACpage/PAC32/PACinfo.html>.

The Lab Resources Requirements List, Hazard Identification Checklist, 
and Computing Requirements List normally included in PAC submissions are 
not required for the 12 GeV PAC

*_NOTE:_*

For all proposals copies will be made in B&W. If color copies are 
preferred, provide 10 copies with your original, along with the 
electronic version of your proposal.


  Reference Material Hard Copies

If you would like any of the materials on the Web sent to you, please 
contact User Liaison via phone (757-269-6388), fax (757-269-6134) or 
e-mail (users at jlab.org).




More information about the Cuga mailing list