[Cuga] JLab schedule/status - A message from R. Ent and A. Freyberger for the Nuclear Physics Experiment Scheduling Committee
Lorelei Chopard
lorelei at jlab.org
Mon Aug 7 15:37:36 EDT 2017
Dear User Community,
On the morning of Thursday July 27th, CHL1 suffered a power event that
resulted in several (but not all) CHL1 compressors tripping off. The
tripped compressors resulted in a path to atmosphere to allow for
gaseous He to escape (which is the nominal situation when *all
*compressors trip off). Unfortunately several compressors remain active
and this resulted in a large volume of air being pulled into the CHL1
Helium space. CHL1 was severely contaminated and inoperable at this point.
At this point in the Summer shutdown, CEBAF was at 4K on CHL1 and CHL2
was at room temperature for maintenance, but in an operable state
(maintenance more or less completed). The estimate was that CEBAF could
last about 48h without 4K CHL operations. CHL2 cooldown started mid-day
Thursday and CEBAF slowly lost LHe levels (clean gas was captured, dirty
gas was vented). CHL2 was able to liquefy Helium Saturday afternoon at
which time several modules had past the no-return point. Cryo cooled and
maintained modules that had not passed the 50K level and those that had
were allowed to warm up to room temperature.
By Sunday about half of CEBAF was cold (but not full). By Monday
Cryogenics had cleaned contaminated purifier and was in the position to
purify He gas and fill some of the modules that were cold. This effort
continues to this day. Next week Cryogenics and SRF will start the
process of cooling down the warm modules. This process will take a bit
less than one-month.
At the time of the incident, two months of shutdown work remained to be
performed, including testing/recommission cold-box SC1 which failed in
March. We are still evaluating the tasks/sequence to recover CEBAF. The
estimate is that sometime around mid-November CEBAF will be in a
position to support beam, with beams for Physics after Thanksgiving.
This is a very rough estimate. We are working on an experiment schedule
for the remaining of 2017 and all of 2018 based on this estimate.
This event is what Ops refers to as a "unplanned" warmup, not to be
confused with an "uncontrolled" warmup (aka hurricane Isabel). As such
the modules warmed in a slow manner as vacuum was maintained during the
warmup (although we wish it was slower). Nevertheless there might be
some impact to SRF performance associated with this event. We are
working with Cryogenics to develop the quickest route to 2K so that we
can evaluate the SRF performance. In the meantime, assuming worse case,
we are readying the two hottest cryomodules in the LERF to be installed
in CEBAF if it is determined that there is a need for this action. The
present sketch suggests that we might be in a position to answer these
questions by Oct.
The Lab Director has formed a Root Cause Investigate team, led by COO
Mike Maier to look into the root cause of this event and recommend
corrective actions.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/cuga/attachments/20170807/aa3474f1/attachment.html>
More information about the Cuga
mailing list