[Dlsupport] Installation down activities
Peter Francis
francis at jlab.org
Tue Jul 19 17:45:45 EDT 2016
For the Run after 8/16/16 how does the IR beam line differ from the IR beam line we are currently working on?
Is there more bpms being added or bpms being removed?
I thought the configuration we are currently working on is the configuration for the engineering run for a week
followed by the real run.
----- Original Message -----
From: "Stephen Benson" <felman at jlab.org>
To: dlsupport at jlab.org
Sent: Tuesday, July 19, 2016 4:26:23 PM
Subject: [Dlsupport] Installation down activities
Please look over the attached schedule with an eye towards realizibility and resource conflicts. Also please let me know what I have missed ( I sure there are several things I have missed).
Steve Benson