[Dlsupport] Questions for the detector installations
Joseph Gubeli
gubeli at jlab.org
Mon Jul 25 15:00:45 EDT 2016
Hi Steve,
For consistency we should call the Moeller OTR viewer and controls 4F06B.
4F06 and 4F06A, like Keith wrote, are needed for LDR to obtain it's three
positions.
Cheers, Joe
-----Original Message-----
From: Dlsupport [mailto:dlsupport-bounces at jlab.org] On Behalf Of Stephen
Benson
Sent: Monday, July 25, 2016 1:23 PM
To: Michael McCaughan <michaelm at jlab.org>
Cc: darklight <darklight at mit.edu>; dlsupport at jlab.org
Subject: Re: [Dlsupport] Questions for the detector installations
I think we are using the old 4F06B channel because we are using the old
4F06A channel for the LDR. The nomenclature for the new viewer is 4F06A
however.
Steve Benson
On Jul 25, 2016, at 1:17 PM, Michael McCaughan <michaelm at jlab.org> wrote:
> Keith,
> Did you mean 4F06B (BVC1:Ch43) for the OTR? Just let me know so I can
add it to the viewer commander.
> Mike
>
> ----- Original Message -----
> From: "Keith Cole" <colek at jlab.org>
> To: "Stephen Benson" <felman at jlab.org>
> Cc: "darklight" <darklight at mit.edu>, dlsupport at jlab.org
> Sent: Monday, July 25, 2016 1:08:58 PM
> Subject: Re: [Dlsupport] Questions for the detector installations
>
> Steve,
> The LDR viewer is using controls for ITV4F06 & ITV4F06A, we would like
to use ITV4F04B controls for the OTR.
>
> ----- Original Message -----
> From: "Stephen Benson" <felman at jlab.org>
> To: "Omar Garza" <garza at jlab.org>
> Cc: "darklight" <darklight at mit.edu>, dlsupport at jlab.org
> Sent: Monday, July 25, 2016 11:45:28 AM
> Subject: Re: [Dlsupport] Questions for the detector installations
>
> Oops, I meant viewer, not valve. ITV4F06A.
>
> Steve
>
> On Jul 25, 2016, at 11:41 AM, Stephen Benson < felman at jlab.org > wrote:
>
>
>
>
> MIT is providing all the instrumentation for the gas handling system.
They will be providing PVs for monitoring purposes but not for control.
> The only think we might need on the Moeller dump is a thermal probe. At
this point it is not called out but, if we have vacuum problems that look
like heating, we might have to add a couple.
> There is only valve that was not available in time for the engineering
run that I hope we can get in for the target run. It is just upstream of
the Moeller dump and is in the nomenclature but it is masked during the
engineering run. It will be a standard OTR viewer with standard controls.
I don't know of any other instrumentation that the DarkLight project might
need.
>
> Steve Benson
>
> On Jul 25, 2016, at 11:17 AM, Omar Garza < garza at jlab.org > wrote:
>
>
>
>
>
>
> Addition questions from The JLAB I&C Group.
>
> Does the gas handling system require additional instrumentation from the
I&C?
>
> Does the moeller dump require any/or additional instrumentation from the
I&C?
>
> Are there any additional sensors, instrumentation, controls, that may
require our assistance?
>
> Thanks.
>
> Omar
>
>
>
>
> On 7/25/2016 9:49 AM, Stephen Benson wrote:
>
>
>
> Here are questions that Anthony DiPette had for the installation:
>
>
> Who is doing the installation work for the Dark Light
Exp. In the LERF 4F Sub 3 region.
> MIT staff, JLab INST Group, other?
>
> If JLab INST Group we will need the following questions answered: -
>
> Which ASME Code do we work to, a single one, fluid based
or system i.e: - LCW, Air, etc.
> Mechanical drawings: -
> Are we field engineering based on a marked up P&ID?
Minimally need something showing approved size & matl to be used?
> Are we getting Mechanical drawings showing approved
fabrication details?
> Some Combination of 1 & 2?
> Materials: -
> Are they on order, awaiting delivery, status, etc?
> Do we need to order material's, if so what kind of
documentation does the code require?
> Is there a list detailing what needs to ordered and
quantity?
> Who is responsible for procurement's & documentation?
> What project code do we use? LERFDL, LERFMT,????
> Are there any "Controlled Materials" needing
controlled storage?
> Is there any welding involved? If so what procedure
does the welder need to be qualified to?
> Pressure System Documentation: -
> What is required?
> Who will generate and maintain it?
> What testing is required?
> Who will do the QA/QC, inspections?
>
> Feedback is desired for these items.
>
> Steve Benson
>
>
> _______________________________________________
> Dlsupport mailing list Dlsupport at jlab.org
https://mailman.jlab.org/mailman/listinfo/dlsupport
>
> <garza.vcf>
>
> _______________________________________________
> Dlsupport mailing list
> Dlsupport at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dlsupport
>
>
> _______________________________________________
> Dlsupport mailing list
> Dlsupport at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dlsupport
> --
> Keith Cole
> EESICS
> Thomas Jefferson National Accelerator Facility
> 600 Kelvin Drive
> Suite 2
> Newport News VA 23606
> Phone 757-269-5920
>
> _______________________________________________
> Dlsupport mailing list
> Dlsupport at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dlsupport
_______________________________________________
Dlsupport mailing list
Dlsupport at jlab.org
https://mailman.jlab.org/mailman/listinfo/dlsupport
More information about the Dlsupport
mailing list