[Dlsupport] HCO status

Stephen Benson felman at jlab.org
Sat Jul 30 09:07:04 EDT 2016


There are currently 4 items that are “Not Ready” in the HCO for the LERF.  They are all with magnet systems (mainly shunts) and are detailed in LERFlog 3415422.  There are also 30 items that have been checked but are not signed off.  Please look over the Hot Check-Out lists to see if you are supposed to sign off on any of these remaining 30 items and sign them off if appropriate.  We are almost there and are far enough along to run beam.  Thanks.