[Dsg-halla_gem] SBS testing and assembly in EEL 124

Marc Mcmullen mcmullen at jlab.org
Fri Apr 23 10:55:40 EDT 2021


Hi Brad,

During our last meeting we discussed the timeline for the completion of the SBS GEM assembly.

This was brought up during the RICH meeting this morning. The RICH electronics assembly and testing occupies the same area that the SBS is currently occupying. The RICH collaboration will need to start assembling the electronics in that area on August 2.

Will the GEM detectors, equipment, and materials be removed by July 30?

Regards,
Marc McMullen