Hello Probir,

Below find the status of the tasks performed by DSG this week.

I&C Drawings

  *
Completed modifications for RTD temperature sensors wiring drawings for all magnets (Information for TM0 needs to be confirmed, for now, assumed that wiring connections are the same as TM1, TM2, and TM3). Revision is required and planed for next week.
  *
Worked on Voltage Taps wiring diagram for TM0.
  *
PLC Watchdog and PLC 1, Slot #3, Digital Output Module drawings are in progress.

NX12 3D Model Rack

  *
Modeled and placed all 24-V power distribution components on the back of the PLC rack model.
  *
Modeled and placed all terminal blocks for the RTD temperature sensors' connections, we're still evaluating the best location of these terminal blocks in the rack; might need to relocated them based on the space required for the relays.

PLC Programming

  *
Rewriting PLC code to cycle through one command per magnet power supply, one supply at a time, instead of all commands per magnet power supply. Ensuring that code increments the loops and resets the indices properly.


Regards,
Pablo
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-halla_moller/attachments/20250530/3c7c7ebb/attachment.htm>


More information about the dsg-halla_moller mailing list