[Dsg-hallbgas] [Dsg-internal] Pressure Systems work for Hall B N2 distribution system

Amrit Yegneswaran yeg at jlab.org
Mon May 7 19:02:45 EDT 2018


marc, 
thanks for informing denny and bob about the lead time needed to set up alternate N2 supply for the RICH aerogel , (as confirmed by george) and thus concluding the matter. 
amrit 


From: "Marc Mcmullen" <mcmullen at jlab.org> 
To: "dsg-hallbgas" <dsg-hallbgas at jlab.org>, "dsg-rich" <dsg-rich at jlab.org>, "Denny Insley" <dinsley at jlab.org> 
Cc: "Patrizia Rossi" <rossi at jlab.org> 
Sent: Monday, May 7, 2018 3:09:14 PM 
Subject: Re: [Dsg-hallbgas] [Dsg-internal] Pressure Systems work for Hall B N2 distribution system 



Hi Denny and Bob, 

Just a recap of this morning's conversation, DSG will need at least two weeks notice of any work which would cause an interruption of N2 to Hall B. This will give enough time to order high pressure LN2 dewars to be delivered to the hall. This will ensure that the Aerogel has a continuous source of N2 at all times to prevent the absorption of moisture. 

Thanks, 

Marc 

On 5/4/2018 3:57 PM, Amrit Yegneswaran wrote: 



thanks for the explanation george. 
i guess we need liquid N2 cylinders for the RICH, if not high purity N2 cylinders. 
we have to coordinate closely with denny so that we have N2 before hallB engineering starts work. 
amrit 


From: "George Jacobs" <jacobsg at jlab.org> 
To: "Amrit Yegneswaran" <yeg at jlab.org> 
Sent: Thursday, May 3, 2018 4:02:31 PM 
Subject: Re: [Dsg-internal] Pressure Systems work for Hall B N2 distribution system 

Hi Amrit, 

This was work in progress that was interrupted for the run. 

I specified the requirement for a temporary alternative N2 supply to maintain the RICH aerogel purge during the outage. 

The work plus pressure testing could take a week or longer. It's important to complete all the required work to eliminate the need for subsequent N2 outages. 

The hot work, brazing the fittings for the relief valve, and it's detailed QA requirements, will drive the timing of this work. Then once all the tasks have been accomplished, pressure testing will require at least a day, maybe more. 

The bottom line is that this must be well planned. 

George 

On 5/3/2018 1:50 PM, Amrit Yegneswaran wrote: 

BQ_BEGIN

george, 
was this e-mail of yours in response to a request from someone in HallB, or is it from your bucket list. 
work must be scheduled such that there is no interruption N2 flow to the RICH. 
more on monday. 
amrit 


From: "George Jacobs" <jacobsg at jlab.org> 
To: "Bob Miller" <rmiller at jlab.org> , "Dave Kashy" <kashy at jlab.org> , "Volker Burkert" <burkert at jlab.org> , "Stepan Stepanyan" <stepanya at jlab.org> , "dsg-internal" <dsg-internal at jlab.org> 
Sent: Thursday, May 3, 2018 11:11:49 AM 
Subject: [Dsg-internal] Pressure Systems work for Hall B N2 distribution system 

Hi Bob, 

The pressure systems work for the Hall B N2 distribution system is incomplete. This work was placed on hold until after this run period. This work requires isolation of the Hall B N2 gas supply. A temporary alternative N2 supply will be required to maintain the RICH aerogel purge during the outage. 

Dave Kashy is the DA on this system. 

The following tasks are outstanding; 
- Relief valve installation 
- Fwd Carriage flex line replacement 
- RICH N2 supply valve relocation 
The following task is NEW; 
- RICH N2 supply capacity increase (Upgrade) 
Re-purpose existing ½” gas line to double flow capacity to FWD Carriage to prepare for 2nd RICH N2 flow requirements 

I have attached a pdf showing the N2 supply P&I diagram with the piping changes in red. I have also attached a pdf showing the relief valve installation detail. All the components required for the relief valve installation were stored in the gas shed prior to this run. 

George 
-- 
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606

(office) 757-269-7115

(cell)   757-876-0480

(email) jacobsg at jlab.org (website) https://userweb.jlab.org/~jacobsg 

_______________________________________________ 
Dsg-internal mailing list 
Dsg-internal at jlab.org 
https://mailman.jlab.org/mailman/listinfo/dsg-internal 


_______________________________________________
Dsg-internal mailing list Dsg-internal at jlab.org https://mailman.jlab.org/mailman/listinfo/dsg-internal 



-- 
George Jacobs
Jefferson Lab (TJNAF)
STE 12
12000 Jefferson Ave.
Newport News, VA 23606

(office) 757-269-7115

(cell)   757-876-0480

(email) jacobsg at jlab.org (website) https://userweb.jlab.org/~jacobsg 



_______________________________________________
Dsg-internal mailing list Dsg-internal at jlab.org https://mailman.jlab.org/mailman/listinfo/dsg-internal 

BQ_END

-- 
Marc McMullen
Detector Support Group
757-269-7738 

_______________________________________________ 
Dsg-hallbgas mailing list 
Dsg-hallbgas at jlab.org 
https://mailman.jlab.org/mailman/listinfo/dsg-hallbgas 
G 
M 
T 
		
		
	
	
	
	
Text-to-speech function is limited to 200 characters 
	
	Options : History : Feedback : Donate 	Close 
-------------- next part --------------
An HTML attachment was scrubbed...