[Dsg-hallb_magnets] Preparation for next Torus power up
Pablo Campero
campero at jlab.org
Tue Jan 10 13:43:10 EST 2017
Hello Amrit,
This the task list for the Torus power up. We will have a meeting on Friday discus the list.
Pablo.
From: "Sarin Philip" <philip at jlab.org>
To: "Ruben Fair" <rfair at jlab.org>, "Dave Kashy" <kashy at jlab.org>, "Probir Ghoshal" <ghoshal at jlab.org>, "Krister Bruhwel" <bruhwel at jlab.org>, "Scot Spiegel" <spiegel at jlab.org>, "Tyler Lemon" <tlemon at jlab.org>, "Pablo Campero Rojas" <campero at jlab.org>, "Nicholas Sandoval" <sandoval at jlab.org>, "Wesley Moore" <wmoore at jlab.org>, "George Biallas" <biallas at jlab.org>, "Bob Miller" <rmiller at jlab.org>, "David Anderson" <dla at jlab.org>
Sent: Tuesday, January 10, 2017 10:13:55 AM
Subject: Re: Preparation for next Torus power up
Good Morning Ruben,
Dave Gelhaar will be the point of contact, Onish will be the backup.
I will discuss with them at our group meeting today morning.
Thanks,
Sarin
On 1/9/2017 11:54 AM, Ruben Fair wrote:
The following is a new meeting request:
Subject: Preparation for next Torus power up
Organizer: "Ruben Fair" <rfair at jlab.org> Time: Friday, January 13, 2017, 9:00:00 AM - 10:00:00 AM GMT -05:00 US/Canada Eastern Required: kashy at jlab.org ; ghoshal at jlab.org ; bruhwel at jlab.org ; spiegel at jlab.org ; tlemon at jlab.org ; campero at jlab.org ; sandoval at jlab.org ; wmoore at jlab.org ; philip at jlab.org ; biallas at jlab.org
Optional: rmiller at jlab.org ; dla at jlab.org
*~*~*~*~*~*~*~*~*~*
Sarin,
We may need some help with the power suppl checks - can you spare either Onish or Dave to work with Krister on this?
Wesley, Krister,
If you are not available, I shall update you later.
George,
As Dave A is not available, please attend to take on any of the vacuum-related items
The next full field power up of the Torus is scheduled to start the week beginning 30th Jan to be ready for the KPP beam run on 03rd Feb.
The Torus is presently at about 80 K.
Present vacuum level is approx. 1E-5 Torr.
It will take approx. 48 hours to get to 4.5K
Therefore the tentative plan will be as follows - so get prepared!
If anyone is going to be on vacation or away from the lab during the time periods indicated below, please let me know now.
A. 09th Jan 2017 - Completion of final Torus Punchlist - essential items only (Dave K, Ruben, Nick, Wesley, Krister, George, Denny, Probir)
B. 16th Jan 2017 - Start pre-cool down checklists (Tyler, Nick, Dave K)
Start vacuum checklist (Dave A, Nick)
Start pre-power up checklists (Probir, Ruben, Pablo, Krister)
C. 18th Jan 2017 - Start of cool down (Dave K, Nick)
Continuation of pre-power up checklists (Probir, Ruben, Pablo, Krister)
D. 23rd Jan 2017 - Low current power-up to 100 A, 200 A, 300 A (Probir, Ruben, Pablo, Krister)
Data acquisition check
Data archiver check
Alarms check
E. 30th Jan 2017 - Power up to full field
F. 03rd Feb 2017 - KPP Beam Run
--
Group Leader
DC Power & Magnets, EES
Jefferson Lab
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170110/316034f0/attachment-0001.html>
More information about the Dsg-hallb_magnets
mailing list