[Dsg-hallb_magnets] Hall B Solenoid - Axial Load Cells
Ruben Fair
rfair at jlab.org
Mon Jul 10 17:31:05 EDT 2017
Excellent - thank you so much guys
Ruben
> On Jul 10, 2017, at 5:20 PM, Pablo Campero <campero at jlab.org> wrote:
>
> Hello Ruben,
>
> The following task were completed today:
>
> Scot / Pablo - connected all axial and radial load cells.
> Brian - completed the changes in the Sol-LV-cRIO program to replace axial load cell (AL-01) with the new one.
> Brian/Pablo - Verified readout for axial and radial load cells, values as we expected:
> The maximum variation with regards to the last measurements (compared with FUTEK measurements) was about 500 lbf. for the radial load cells.
> Max readout for axial load cells was about 120 lbf.
>
> All load cell connectors were disconnected right before 4 pm today to allow the welding work in the Solenoid.
> Axial load test will continue tomorrow morning.
>
> Best Regards,
> Pablo
>
> From: "Ruben Fair" <rfair at jlab.org>
> To: "Pablo Campero" <campero at jlab.org>, "Scot Spiegel" <spiegel at jlab.org>, "Brian Eng" <beng at jlab.org>, "Tyler Lemon" <tlemon at jlab.org>, "Wesley Moore" <wmoore at jlab.org>
> Cc: "Dave Kashy" <kashy at jlab.org>, "Joseph Matalevich" <josephm at jlab.org>, "Renuka Rajput-Ghoshal" <renuka at jlab.org>
> Sent: Sunday, July 9, 2017 7:27:57 AM
> Subject: Hall B Solenoid - Axial Load Cells
>
> Chaps,
>
> By Thursday morning 13th July, can you please complete the following:
>
> 1. Fit all axial load cells to OVC and connectorize - Scot
>
> 2. Complete all lookup tables for each load cell for readings in pounds instead of kN - Brian
>
> 3. Update all master Excel sheets to display both pounds and kN and update all calculations and limits to work and display in pounds (Excel, PLC and EPICS) - Pablo / Wesley
>
> 3. Connect cabling and check axial load cell readouts on EPICS - Scot / Pablo
>
> Please work with Joe Matalevich (Sub Team Lead for Welding) to allow you to do this when they are not welding.
>
> Please remember to re-fit the conductive (shorting) foam pads in the Magnet feedthrus after doing your work and disconnecting instrumentation cables.
>
> Regards
>
> Ruben
>
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20170710/e3b6eb3f/attachment.html>
More information about the Dsg-hallb_magnets
mailing list