FYI, see Ruben's comment below about the magnet schedule.

Next week is the last one to do major changes to the Hall B Magnets, i.e. stuff that needs to be taken offline.

> Begin forwarded message:
> 
> From: Ruben Fair <rfair at jlab.org>
> Subject: Hall B - E-stops (Torus and Solenoid) / QD boards (Solenoid), RV heaters (Solenoid)
> Date: July 5, 2018 at 7:43:59 AM EDT
> 
> As the Hall B magnets are likely to start their cool down on July 16th, the work on the E-Stops and QD boards will need to be completed by Friday 13th July.