[Dsg-hallb_magnets] Fwd: Hall B - E-stops (Torus and Solenoid) / QD boards (Solenoid), RV heaters (Solenoid)

Amrit Yegneswaran yeg at jlab.org
Fri Jul 6 11:26:51 EDT 2018


thanks for forwarding the e-mail brian. 
what is this major stuff? 
what is dsg's role? 
given our current work load is this possible? 



From: "Brian Eng" <beng at jlab.org> 
To: "dsg-hallb magnets" <dsg-hallb_magnets at jlab.org> 
Sent: Friday, July 6, 2018 9:27:54 AM 
Subject: [Dsg-hallb_magnets] Fwd: Hall B - E-stops (Torus and Solenoid) / QD boards (Solenoid), RV heaters (Solenoid) 

FYI, see Ruben's comment below about the magnet schedule. 

Next week is the last one to do major changes to the Hall B Magnets, i.e. stuff that needs to be taken offline. 





Begin forwarded message: 

From: Ruben Fair < rfair at jlab.org > 
Subject: Hall B - E-stops (Torus and Solenoid) / QD boards (Solenoid), RV heaters (Solenoid) 
Date: July 5, 2018 at 7:43:59 AM EDT 

As the Hall B magnets are likely to start their cool down on July 16th, the work on the E-Stops and QD boards will need to be completed by Friday 13th July. 





_______________________________________________ 
Dsg-hallb_magnets mailing list 
Dsg-hallb_magnets at jlab.org 
https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets 
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20180706/715b53aa/attachment.html>


More information about the Dsg-hallb_magnets mailing list