Thank you Pablo and the DSG.
Ruben
> On Jul 26, 2018, at 5:12 PM, Pablo Campero <campero at jlab.org> wrote:
>
> Hello,
>
> Today DSG performed the Pre-power up interlock checkouts for the Solenoid and Torus magnets.
> Solenoid Interlock checkouts were almost completed, there is still remaining one task to be completed (Voltage Taps Comparators). So far there is no problems.
> Torus Interlock checkouts were just started, 8 task checked and so far everything is going well.
>
> Tomorrow morning, we will continue the interlocks checkouts.
>
>
> Best Regards,
> Pablo
> _______________________________________________
> Dsg-hallb_magnets mailing list
> Dsg-hallb_magnets at jlab.org
> https://mailman.jlab.org/mailman/listinfo/dsg-hallb_magnets
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <https://mailman.jlab.org/pipermail/dsg-hallb_magnets/attachments/20180726/f5793b62/attachment.html>
More information about the Dsg-hallb_magnets
mailing list